# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
6791 Project progress work New Normal [Internal design] 16.00 0.00 11 Mar 2026 11:32 Actions
6790 Project progress work New Normal [Requirement definition] 0.00 05 Mar 2026 15:06 Actions
6789 Project progress work New Normal [Installation&On-site support] 128.00 0.00 05 Mar 2026 15:31 Actions
6788 Project progress work New Normal [Coding] 0.00 05 Mar 2026 15:05 Actions
3001 Parent project In Progress Normal [PJ250087] Product Distribution System - CPF Anek Sanohkham 144.00 0.00 11 Mar 2026 11:32 Actions