Activity
From 27 May 2026 to 05 Jun 2026
05 Jun 2026
- 16:11 Project progress work #8430 (Closed): [Requirement definition] On-site meeting with customer to discuss the operation flow and system requirements.
- 16:11 Project progress work #8430 (Closed): [Requirement definition] On-site meeting with customer to discuss the operation flow and system requirements.
- 16:10 Project progress work #8429 (New): [Installation&On-site support]
- 16:10 Project progress work #8428 (New): [Coding]
- 16:10 Project progress work #8427 (New): [Internal Design]
- 16:09 Project progress work #8426 (New): [Requirement definition]