Parent project #6939: [PJ260047] ConMas i-Reporter 20 users On-premises
Parent project #5397: [PJ260010] Infrastructure IoT system for NTN Manufacturing(Thailand) Hardware PT
Project progress work #5398: [Requirement Definition]
Project progress work #6458: [Requirement definition] Requirements confirmation
Project progress work #6457: [Requirement definition] Kick-off meeting
Project progress work #5399: [Internal Design]
Project progress work #6459: [Internal Design] System Design
Project progress work #6460: [Coding] Hardware procurement
Project progress work #6461: [Coding] Hardware pre-shipment confirmation
Project progress work #5401: [Installation&On-site support]
Project progress work #6462: [Installation&On-site support] Power Meter installation
Project progress work #6463: [Installation&On-site support] Software installation (PLC)
Project progress work #6464: [Installation&On-site support] Software installation (Application)
Project progress work #6465: [Installation&On-site support] Software installation (Web Application)
Project progress work #6466: [Installation&On-site support] Teaching for UT
Project progress work #6467: [Installation&On-site support] User Testing & Trial
Project progress work #6468: [Inatallation&On-site support] Supports user feedback
Project progress work #6469: [Installation&On-site support] Teaching for Go live
Project progress work #7061: [Installation&On-site support] UAT
Project progress work #6470: [Inatallation&On-site support] Go live

Status

In Progress
In Progress
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New
New

Priority

Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal

Total estimated time

152.00
0.00
0.00
48.00
104.00
56.00

Total spent time

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

Updated

13 Mar 2026 08:38
25 Mar 2026 15:25
06 Feb 2026 11:24
06 Feb 2026 11:24
06 Feb 2026 11:22
06 Feb 2026 11:34
06 Feb 2026 11:34
11 Mar 2026 10:15
06 Feb 2026 11:35
06 Feb 2026 11:36
25 Mar 2026 15:25
06 Feb 2026 11:39
06 Feb 2026 11:42
06 Feb 2026 11:44
06 Feb 2026 11:47
06 Feb 2026 11:49
06 Feb 2026 11:51
06 Feb 2026 11:53
06 Feb 2026 11:54
25 Mar 2026 15:25
06 Feb 2026 11:55
 
 
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Tomas Tech All Project Management
 
 
NTN MANUFACTURING (THAILAND) CO., LTD.
 
 
 
 
 
In Progress
Parent project #5397: [PJ260010] Infrastructure IoT system for NTN Manufacturing(Thailand) Hardware PT

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: In Progress
Start date: 02 Feb 2026
Due date: 22 Mar 2026
Assignee: Nattapol Poeam
Priority: Normal
 
 
 
 
New 0%
Project progress work #5398: [Requirement Definition]

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: New
Start date: 02 Feb 2026
Due date: 08 Feb 2026
Assignee:
Priority: Normal
 
 
New 0%
Project progress work #6458: [Requirement definition] Requirements confirmation

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: New
Start date: 02 Feb 2026
Due date: 08 Feb 2026
Assignee: Konlawat Saechee
Priority: Normal
 
 
New 0%
Project progress work #6457: [Requirement definition] Kick-off meeting

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: New
Start date: 03 Feb 2026
Due date: 03 Feb 2026
Assignee: Konlawat Saechee
Priority: Normal
 
 
 
 
New 0%
Project progress work #5399: [Internal Design]

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: New
Start date: 02 Feb 2026
Due date: 15 Feb 2026
Assignee:
Priority: Normal
 
 
New 0%
Project progress work #6459: [Internal Design] System Design

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: New
Start date: 02 Feb 2026
Due date: 15 Feb 2026
Assignee: Konlawat Saechee
Priority: Normal
 
 
 
 
 
New 33%
Project progress work #5400: [Coding]

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: New
Start date: 09 Feb 2026
Due date: 24 Feb 2026
Assignee:
Priority: Normal
 
 
New 0%
Project progress work #6460: [Coding] Hardware procurement

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: New
Start date: 09 Feb 2026
Due date: 20 Feb 2026
Assignee: Konlawat Saechee
Priority: Normal
 
 
New 0%
Project progress work #6461: [Coding] Hardware pre-shipment confirmation

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: New
Start date: 16 Feb 2026
Due date: 20 Feb 2026
Assignee: Konlawat Saechee
Priority: Normal
 
 
 
 
 
New 24%
Project progress work #5401: [Installation&On-site support]

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: New
Start date: 21 Feb 2026
Due date: 22 Mar 2026
Assignee:
Priority: Normal
 
 
New 0%
Project progress work #6462: [Installation&On-site support] Power Meter installation

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: New
Start date: 21 Feb 2026
Due date: 24 Feb 2026
Assignee: Konlawat Saechee
Priority: Normal
 
 
New 0%
Project progress work #6463: [Installation&On-site support] Software installation (PLC)

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: New
Start date: 25 Feb 2026
Due date: 26 Feb 2026
Assignee: Konlawat Saechee
Priority: Normal
 
 
New 0%
Project progress work #6464: [Installation&On-site support] Software installation (Application)

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: New
Start date: 26 Feb 2026
Due date: 27 Feb 2026
Assignee: Konlawat Saechee
Priority: Normal
 
 
New 0%
Project progress work #6465: [Installation&On-site support] Software installation (Web Application)

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: New
Start date: 26 Feb 2026
Due date: 27 Feb 2026
Assignee: Konlawat Saechee
Priority: Normal
 
 
New 0%
Project progress work #6466: [Installation&On-site support] Teaching for UT

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: New
Start date: 27 Feb 2026
Due date: 27 Feb 2026
Assignee: Konlawat Saechee
Priority: Normal
 
 
New 0%
Project progress work #6467: [Installation&On-site support] User Testing & Trial

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: New
Start date: 28 Feb 2026
Due date: 08 Mar 2026
Assignee: Konlawat Saechee
Priority: Normal
 
 
New 0%
Project progress work #6468: [Inatallation&On-site support] Supports user feedback

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: New
Start date: 28 Feb 2026
Due date: 08 Mar 2026
Assignee: Konlawat Saechee
Priority: Normal
 
 
New 0%
Project progress work #6469: [Installation&On-site support] Teaching for Go live

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: New
Start date: 28 Feb 2026
Due date: 08 Mar 2026
Assignee: Konlawat Saechee
Priority: Normal
 
 
 
New 100%
Project progress work #7061: [Installation&On-site support] UAT

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: New
Start date: 03 Mar 2026
Due date: 10 Mar 2026
Assignee: Suphawat Tinaso
Priority: Normal
 
 
New 0%
Project progress work #6470: [Inatallation&On-site support] Go live

Project: NTN MANUFACTURING (THAILAND) CO., LTD.
Status: New
Start date: 09 Mar 2026
Due date: 22 Mar 2026
Assignee: Konlawat Saechee
Priority: Normal
 