Project progress work #866: [Documentation] Get requirements of project
Parent project #827: [PJ240059] Warehouse system for business improvement for NKT
Project progress work #1130: [Coding] Documentation user manual web
Project progress work #1128: [Requirement definition]
Project progress work #1129: [Internal Design]
Project progress work #843: [Cording] Warehouse system for business improvement for NKT Android
Project progress work #1413: [Coding] Issue found
Project progress work #1414: [Coding] Add checking function of tire and rack
Project progress work #1416: [Coding] Picking plan adjustment
Project progress work #1417: [Coding] Check qty of receiving part
Project progress work #1419: [Coding] Able to scan tag in check stock
Project progress work #1420: [Coding] Transport - internal test
Project progress work #1421: [Coding] Stock tracking - Change location
Project progress work #1418: [Coding] Check duplicated on scan
Project progress work #828: [Cording] Warehouse system for business improvement for NKT PHP
Project progress work #1131: [Installation&On-site support]

Status

New
In Progress
New
New
New
New
New
In Progress
New
New
New
New
New
New
New
New
In Progress
New

Priority

Normal
High
Normal
Normal
Normal
Normal
Normal
High
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal

Total estimated time

80.00
32.00
0.00
16.00
8.00
8.00
8.00

Total spent time

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

Updated

24 Dec 2024 20:49
20 Feb 2026 09:47
11 Sep 2025 14:49
11 Sep 2025 14:48
11 Sep 2025 14:49
05 Nov 2025 16:20
05 Nov 2025 16:20
08 Jun 2025 15:01
08 Nov 2025 10:18
11 Sep 2025 14:53
11 Sep 2025 14:54
11 Sep 2025 14:59
11 Sep 2025 14:56
11 Sep 2025 15:00
11 Sep 2025 14:58
08 Nov 2025 10:43
12 Feb 2026 15:22
20 Feb 2026 09:47
 
 
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Tomas Tech All Project Management
 
 
NKT NIPPON KONPO (THAILAND) CO., LTD
New 50%
 
 
 
In Progress
Parent project #827: [PJ240059] Warehouse system for business improvement for NKT

Project: NKT NIPPON KONPO (THAILAND) CO., LTD
Status: In Progress
Start date: 28 Dec 2024
Due date: 18 Feb 2026
Assignee: Kittisak Isarapongporn
Priority: High
New 100%
New 100%
In Progress 90%
New 87%
New 100%
In Progress 100%
 
 
 
 
 
New 100%
Project progress work #1131: [Installation&On-site support]

Project: NKT NIPPON KONPO (THAILAND) CO., LTD
Status: New
Start date: 18 Feb 2026
Due date: 18 Feb 2026
Assignee: Kittisak Isarapongporn
Priority: Normal
 