Project

General

Profile

Activity

From 09 Jan 2025 to 18 Jan 2025

18 Jan 2025

16:38 4.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
Meeting get requirement with K.Nack. Ronnagon Kongsuwan

16 Jan 2025

22:39 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
Developed and completed Page Import Type Delivery Plan. Ronnagon Kongsuwan
22:38 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
Developed and completed Page Import Type ReceivePlan. Ronnagon Kongsuwan
22:37 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
Developed and completed Item Master. Ronnagon Kongsuwan
22:36 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
Developed and completed Supplier Master. Ronnagon Kongsuwan
22:36 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
Developed and completed Customer Master. Ronnagon Kongsuwan
22:29 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
Developed and completed Page Inbound Material function Material Receive. Ronnagon Kongsuwan
22:28 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
Developed Page Inbound Material function Material Receive. Ronnagon Kongsuwan
22:27 8.00 hours (Project progress work #828 (In Progress): [Cording] Warehouse system for business improvement for NKT PHP)
Developed Material Receive QC Ronnagon Kongsuwan
 