26 Feb 2026

14:19 Project progress work #6760 (Closed): [Coding] re test incominpplan and fix code because change algorithm stock
Waraporn Promsopa
14:18 Project progress work #6760 (Closed): [Coding] re test incominpplan and fix code because change algorithm stock
Waraporn Promsopa
14:13 Project progress work #6759 (Closed): [Coding] Create Qrcode for UserLogin QC , Meeting Present Progress for Team Nippn
Waraporn Promsopa
14:13 Project progress work #6759 (Closed): [Coding] Create Qrcode for UserLogin QC , Meeting Present Progress for Team Nippn
Waraporn Promsopa
14:11 Project progress work #6758 (Closed): [Coding] "update Handy for Fixbug Menu Location In warehouse Print Label Location For Warehouse"
Waraporn Promsopa
14:11 Project progress work #6758 (Closed): [Coding] "update Handy for Fixbug Menu Location In warehouse Print Label Location For Warehouse"
Waraporn Promsopa
14:09 Project progress work #6757 (Closed): [Coding] Add Return PD
Waraporn Promsopa
14:09 Project progress work #6757 (Closed): [Coding] Add Return PD
Waraporn Promsopa
14:08 Project progress work #6756 (Closed): [Coding] Add page sum itemname
Waraporn Promsopa
14:07 Project progress work #6756 (Closed): [Coding] Add page sum itemname
Waraporn Promsopa
14:06 Project progress work #6755 (Closed): [Coding] Edit and Test Stock Card Trigger
Waraporn Promsopa
14:06 Project progress work #6755 (Closed): [Coding] Edit and Test Stock Card Trigger
Waraporn Promsopa
14:05 Project progress work #6754 (Closed): [Coding] Validate Stock Remain when Scan Handy
Waraporn Promsopa
14:05 Project progress work #6754 (Closed): [Coding] Validate Stock Remain when Scan Handy
Waraporn Promsopa
14:04 Project progress work #6576 (In Progress): [Coding]
Waraporn Promsopa
13:20 Project progress work #6749 (Closed): [Coding] export group PTN_00,PTN_01,PTN_02
Waraporn Promsopa
13:20 Project progress work #6749 (Closed): [Coding] export group PTN_00,PTN_01,PTN_02
Waraporn Promsopa
13:17 Project progress work #6748 (Closed): [Coding] Bom change select line and insturtion
Waraporn Promsopa
13:17 Project progress work #6748 (Closed): [Coding] Bom change select line and insturtion
Waraporn Promsopa

24 Feb 2026

15:52 Project progress work #4466 (Closed): [Installation&On-site support] Wiring LAN Cable and config access point
Waraporn Promsopa

19 Feb 2026

15:42 Project progress work #6702 (Closed): [Coding] add floor by
Waraporn Promsopa
15:34 Project progress work #6702 (Closed): [Coding] add floor by
Waraporn Promsopa
15:42 Project progress work #6701 (Closed): [Coding] Bom from tab edit group (PTN_00,PTN_01,PTN_02)
Waraporn Promsopa
15:33 Project progress work #6701 (Closed): [Coding] Bom from tab edit group (PTN_00,PTN_01,PTN_02)
Waraporn Promsopa
15:41 Project progress work #6698 (Closed): [Coding] Bom change select line and insturtion
Waraporn Promsopa
15:28 Project progress work #6698 (Closed): [Coding] Bom change select line and insturtion
Waraporn Promsopa
15:24 Project progress work #6696 (Closed): [Coding] Import Bom
Waraporn Promsopa
15:24 Project progress work #6696 (Closed): [Coding] Import Bom
Waraporn Promsopa
15:22 Project progress work #6695 (Closed): [Coding] Stock FG Menu
Waraporn Promsopa
15:19 Project progress work #6695 (Closed): [Coding] Stock FG Menu
Waraporn Promsopa
15:18 Project progress work #1506 (In Progress): [Coding] Schedule/Non-Schedule