Activity
From 17 Feb 2024 to 26 Feb 2024
23 Feb 2024
- 11:33 8.00 hours (Project progress work #102 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
21 Feb 2024
- 19:13 4.00 hours (Project progress work #442 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- 19:13 5.00 hours (Project progress work #442 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- 19:13 4.00 hours (Project progress work #442 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- 19:13 14.00 hours (Project progress work #442 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- 16:35 8.00 hours (Project progress work #103 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Final day for handy test and system check
- 10:42 8.00 hours (Project progress work #104 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
- 10:41 8.00 hours (Project progress work #104 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
- 10:41 8.00 hours (Project progress work #104 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
- 10:39 8.00 hours (Project progress work #104 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
- 10:39 8.00 hours (Project progress work #104 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
20 Feb 2024
- 15:49 8.00 hours (Project progress work #99 (Closed): [System Testing]Handyterminal and Web)
- final test handy
- 15:47 8.00 hours (Project progress work #447 (Closed): create manual document for MAST)
- create manual handy & web
- 15:43 8.00 hours (Project progress work #102 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
- 15:43 8.00 hours (Project progress work #102 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
- 15:43 8.00 hours (Project progress work #102 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
- 15:42 8.00 hours (Project progress work #102 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
- 15:42 8.00 hours (Project progress work #102 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
- 15:42 8.00 hours (Project progress work #102 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
- 15:41 8.00 hours (Project progress work #102 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
- 08:55 8.00 hours (Project progress work #103 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
- 08:55 8.00 hours (Project progress work #103 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
- 08:55 8.00 hours (Project progress work #103 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
- 08:55 8.00 hours (Project progress work #103 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
- 08:54 8.00 hours (Project progress work #103 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
- 08:54 8.00 hours (Project progress work #103 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
- 08:54 8.00 hours (Project progress work #103 (Closed): [Installation&On-site support]Project Stock management system for MAS-T)
- Installation&On-site support
Also available in: Atom