17:42 Project progress work #97: [Coding]Android handyterminal BTA500
coding label schedule and label detail page Soraya Norasing
15:20 Project progress work #106 (Confirmation request): [System Testing]ST with AS400
Test Import 6 Files OK krub. Kamol Anekchatnuntakool

26 Dec 2023

22:42 Project progress work #97: [Coding]Android handyterminal BTA500
coding schedule label page
Soraya Norasing

25 Dec 2023

22:11 Project progress work #97: [Coding]Android handyterminal BTA500
coding label schedule page Soraya Norasing

22 Dec 2023

22:17 Project progress work #97: [Coding]Android handyterminal BTA500
coding inbound detail page finished Soraya Norasing

20 Dec 2023

19:11 Project progress work #97: [Coding]Android handyterminal BTA500
-inbound schedule finished wait api
tomorrow
coding inbound detail
Soraya Norasing

19 Dec 2023

23:05 Project progress work #97: [Coding]Android handyterminal BTA500
-Find a way to pull up the screen to refresh for refresh schedule page.
-coding schedule adapter view.
Soraya Norasing

18 Dec 2023

23:11 Project progress work #97: [Coding]Android handyterminal BTA500
-change design layout menu page.
-design & coding inbound schedule page & inbound detail
Soraya Norasing
 