- 14:38 Parent project #2703 (Closed): [PJ250065] CKD system for Logistics Alliance (Thailand) CO.,LTD - CYLC 100%
- 14:38 Project progress work #2707 (Closed): [Installation&On-site support]
- 14:38 Project progress work #2706 (Closed): [Coding]
- 14:38 Project progress work #2705 (Closed): [Internal Design]
- 14:38 Project progress work #2704 (Closed): [Requirement definition]
- 14:36 Parent project #2698 (Closed): [PJ250064] CKD modification function Scope: Development of SoW stock CKD end month
- 14:36 Project progress work #2702 (Closed): [Installation&On-site support]
- 14:36 Project progress work #2701 (Closed): [Coding]
- 14:36 Project progress work #2700 (Closed): [Internal Design]
- 14:36 Project progress work #2699 (Closed): [Requirement definition]