19 Nov 2024

17:05 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
Install HT Software. Kamol Anekchatnuntakool
10:09 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
Install HT Software. Kamol Anekchatnuntakool

17 Nov 2024

23:25 8.00 hours (Project progress work #759 (Closed): STEP - Installation)
[Task] LAT - STEP - Installation 5/5 Thanthima Phaengkham
23:25 8.00 hours (Project progress work #759 (Closed): STEP - Installation)
[Task] LAT - STEP - Installation 4/5 Thanthima Phaengkham
23:25 8.00 hours (Project progress work #759 (Closed): STEP - Installation)
[Task] LAT - STEP - Installation 3/5 Thanthima Phaengkham
23:25 8.00 hours (Project progress work #759 (Closed): STEP - Installation)
[Task] LAT - STEP - Installation 2/5 Thanthima Phaengkham
23:24 8.00 hours (Project progress work #759 (Closed): STEP - Installation)
[Task] LAT - STEP - Installation 1/5 Thanthima Phaengkham
23:23 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
[Task] LAT - PICS - Installation 5/15 Thanthima Phaengkham
23:23 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
[Task] LAT - PICS - Installation 4/15 Thanthima Phaengkham
23:22 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
[Task] LAT - PICS - Installation 3/15 Thanthima Phaengkham
23:22 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
[Task] LAT - PICS - Installation 2/15 Thanthima Phaengkham
23:22 8.00 hours (Project progress work #758 (Closed): PICS - Installation)
[Task] LAT - PICS - Installation 1/15 Thanthima Phaengkham

16 Nov 2024

16:52 8.00 hours (Project progress work #735 (Closed): PICS handy terminal Document.)
Check HT Software. Kamol Anekchatnuntakool

15 Nov 2024

16:48 8.00 hours (Project progress work #735 (Closed): PICS handy terminal Document.)
Make Document HT Software. Kamol Anekchatnuntakool

14 Nov 2024

17:00 8.00 hours (Project progress work #735 (Closed): PICS handy terminal Document.)
Make Document HT Software. Kamol Anekchatnuntakool

13 Nov 2024

16:47 8.00 hours (Project progress work #735 (Closed): PICS handy terminal Document.)
Make Document HT Software. Kamol Anekchatnuntakool

12 Nov 2024

16:55 8.00 hours (Project progress work #735 (Closed): PICS handy terminal Document.)
Make Document HT Software. Kamol Anekchatnuntakool

11 Nov 2024

16:46 8.00 hours (Project progress work #735 (Closed): PICS handy terminal Document.)
Make Document HT Software. Kamol Anekchatnuntakool
14:14 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 21/30 Thanthima Phaengkham
14:14 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 20/30 Thanthima Phaengkham
14:13 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 19/30 Thanthima Phaengkham
14:13 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 18/30 Thanthima Phaengkham
14:13 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 17/30 Thanthima Phaengkham
14:13 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 16/30 Thanthima Phaengkham
14:12 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 15/30 Thanthima Phaengkham
14:12 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 14/30 Thanthima Phaengkham
14:12 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 13/30 Thanthima Phaengkham
14:12 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 12/30 Thanthima Phaengkham
14:10 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 11/30 Thanthima Phaengkham
14:10 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 10/30 Thanthima Phaengkham
14:10 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 9/30 Thanthima Phaengkham
14:09 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 8/30 Thanthima Phaengkham
14:09 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 7/30 Thanthima Phaengkham
14:09 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 6/30 Thanthima Phaengkham
14:09 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 5/30 Thanthima Phaengkham
14:08 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 4/30 Thanthima Phaengkham
14:08 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 3/30 Thanthima Phaengkham
14:08 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 2/30 Thanthima Phaengkham
14:07 8.00 hours (Project progress work #495 (Closed): SALE - Version upgrade development support)
[Task] LAT - SALE - Conversion and Documents Creation 1/30 Thanthima Phaengkham
14:03 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
[Task] LAT - STEP - Conversion and Documents Creation 30/30 Thanthima Phaengkham
14:03 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
[Task] LAT - STEP - Conversion and Documents Creation 29/30 Thanthima Phaengkham
14:02 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
[Task] LAT - STEP - Conversion and Documents Creation 28/30 Thanthima Phaengkham
14:02 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
[Task] LAT - STEP - Conversion and Documents Creation 27/30 Thanthima Phaengkham
14:02 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
[Task] LAT - STEP - Conversion and Documents Creation 26/30 Thanthima Phaengkham
14:01 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
[Task] LAT - STEP - Conversion and Documents Creation 25/30 Thanthima Phaengkham
14:01 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
[Task] LAT - STEP - Conversion and Documents Creation 24/30 Thanthima Phaengkham
14:01 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
[Task] LAT - STEP - Conversion and Documents Creation 23/30 Thanthima Phaengkham
14:01 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
[Task] LAT - STEP - Conversion and Documents Creation 22/30 Thanthima Phaengkham
14:00 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
[Task] LAT - STEP - Conversion and Documents Creation 21/30 Thanthima Phaengkham
14:00 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
[Task] LAT - STEP - Conversion and Documents Creation 20/30 Thanthima Phaengkham
14:00 8.00 hours (Project progress work #494 (Closed): STEP - Version upgrade development support)
[Task] LAT - STEP - Conversion and Documents Creation 19/30 Thanthima Phaengkham
13:58 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
[Task] LAT - REPO - Conversion and Documents Creation 35/36 Thanthima Phaengkham
13:58 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
[Task] LAT - REPO - Conversion and Documents Creation 34/36 Thanthima Phaengkham
13:58 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
[Task] LAT - REPO - Conversion and Documents Creation 33/36 Thanthima Phaengkham
13:58 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
[Task] LAT - REPO - Conversion and Documents Creation 32/36 Thanthima Phaengkham
13:57 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
[Task] LAT - REPO - Conversion and Documents Creation 31/36 Thanthima Phaengkham
13:57 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
[Task] LAT - REPO - Conversion and Documents Creation 30/36 Thanthima Phaengkham
13:57 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
[Task] LAT - REPO - Conversion and Documents Creation 29/36 Thanthima Phaengkham
13:57 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
[Task] LAT - REPO - Conversion and Documents Creation 28/36 Thanthima Phaengkham
13:56 8.00 hours (Project progress work #493 (Closed): REPO - Version upgrade development support)
[Task] LAT - REPO - Conversion and Documents Creation 27/36 Thanthima Phaengkham
13:55 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
[Task] LAT - CYLC - Conversion and Documents Creation 36/36 Thanthima Phaengkham
13:55 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
[Task] LAT - CYLC - Conversion and Documents Creation 35/36 Thanthima Phaengkham
13:54 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
[Task] LAT - CYLC - Conversion and Documents Creation 34/36 Thanthima Phaengkham
13:54 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
[Task] LAT - CYLC - Conversion and Documents Creation 33/36 Thanthima Phaengkham
13:54 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
[Task] LAT - CYLC - Conversion and Documents Creation 32/36 Thanthima Phaengkham
13:53 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
[Task] LAT - CYLC - Conversion and Documents Creation 31/36 Thanthima Phaengkham
13:53 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
[Task] LAT - CYLC - Conversion and Documents Creation 30/36 Thanthima Phaengkham
13:53 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
[Task] LAT - CYLC - Conversion and Documents Creation 29/36 Thanthima Phaengkham
13:52 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
[Task] LAT - CYLC - Conversion and Documents Creation 28/36 Thanthima Phaengkham
13:52 8.00 hours (Project progress work #492 (Closed): CYLC - Version upgrade development support)
[Task] LAT - CYLC - Conversion and Documents Creation 27/36 Thanthima Phaengkham
 