12 Sep 2024
- 17:01 8.00 hours (Project progress work #662 (Closed): PICS - Version upgrade development support handy terminal)
- Modify HT Software.
11 Sep 2024
- 16:47 8.00 hours (Project progress work #662 (Closed): PICS - Version upgrade development support handy terminal)
- Modify HT Software.
- 15:44 8.00 hours (Project progress work #491 (Closed): PICS - Version upgrade development support)
- [Task] LAT - PICS- Conversion and Documents Creation
10 Sep 2024
- 16:57 8.00 hours (Project progress work #662 (Closed): PICS - Version upgrade development support handy terminal)
- Modify HT Software.
- 10:24 8.00 hours (Project progress work #715 (Closed): CAPS - Installation)
- [Task] LAT - CAPS - Installation 5/10
- 10:24 8.00 hours (Project progress work #715 (Closed): CAPS - Installation)
- [Task] LAT - CAPS - Installation 4/10
- 10:23 8.00 hours (Project progress work #715 (Closed): CAPS - Installation)
- [Task] LAT - CAPS - Installation 3/10
- 10:22 8.00 hours (Project progress work #715 (Closed): CAPS - Installation)
- [Task] LAT - CAPS - Installation 2/10
- 10:22 8.00 hours (Project progress work #715 (Closed): CAPS - Installation)
- [Task] LAT - CAPS - Installation 1/10
- 10:16 232.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- 10:16 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 29/29
- 10:16 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 28/29
- 10:16 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 27/29
- 10:15 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 26/29
- 10:15 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 25/29
- 10:15 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 24/29
- 10:14 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 23/29
- 10:13 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 22/29
- 10:13 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 21/29
- 10:13 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 20/29
- 10:13 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 19/29
- 10:12 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 18/29
- 10:12 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 17/29
- 10:12 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 16/29
- 10:11 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 15/29
- 10:11 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 14/29
- 10:11 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 13/29
- 10:10 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 12/29
- 10:08 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 11/29
- 10:08 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 10/29
- 10:08 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 9/29
- 10:07 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 8/29
- 10:07 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 7/29
- 10:07 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 6/29
- 10:07 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 5/29
- 10:06 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 4/29
- 10:06 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 3/29
- 10:06 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 2/29
- 10:05 8.00 hours (Project progress work #489 (Closed): SALE - Operation test confirmation/Specification creation)
- [Task] LAT - SALE - Operation test confirmation/Specification creation 1/29
- 10:04 232.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- 10:03 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 29/29
- 10:03 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 28/29
- 10:03 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 27/29
- 10:03 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 26/29
- 10:02 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 25/29
- 10:02 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 24/29
- 10:02 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 23/29
- 10:02 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 22/29
- 10:01 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 21/29
- 10:01 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 20/29
- 10:01 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 18/29
- 10:00 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 17/29
- 10:00 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 17/29
- 10:00 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 16/29
- 10:00 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 15/29
- 09:59 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 14/29
- 09:59 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 13/29
- 09:59 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 12/29
- 09:59 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 11/29
- 09:58 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 10/29
- 09:58 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 9/29
- 09:54 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 7/29
- 09:53 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 6/29
- 09:50 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 4/29
- 09:49 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- STEP - Operation test confirmation/Specification creation 2/29
- 09:49 8.00 hours (Project progress work #488 (Closed): STEP - Operation test confirmation/Specification creation)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 2/29
- 09:53 8.00 hours (Parent project #542 (Closed): [PJ240019] CKD system for Logistics Alliance (Thailand) CO.,LTD CYLC)
- [Task] LAT - STEP - Operation test confirmation/Specification creation 5/29
- 09:42 232.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- 09:41 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 29/29
- 09:41 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 28/29
- 09:40 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 27/29
- 09:40 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 26/29
- 09:40 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 25/29
- 09:39 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 24/29
- 09:39 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 23/29
- 09:39 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 22/29
- 09:38 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 21/29
- 09:32 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 19/29
- 09:31 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 20/29
- 09:31 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 19/29
- 09:31 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 18/29
- 09:31 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 17/29
- 09:30 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 16/29
- 09:30 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 14/29
- 09:29 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 15/29
- 09:29 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 14/29
- 09:29 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 13/29
- 09:26 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 12/29
- 09:26 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 11/29
- 09:26 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 10/29
- 09:25 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 9/29
- 09:25 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 8/29
- 09:25 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 7/29
- 09:25 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 6/29
- 09:24 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 5/29
- 09:24 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 4/29
- 09:24 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 3/29
- 09:23 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 2/29
- 09:23 8.00 hours (Project progress work #487 (Closed): REPO - Operation test confirmation/Specification creation)
- [Task] LAT - REPO - Operation test confirmation/Specification creation 1/29
- 09:21 192.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- 09:18 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 24/24
- 09:17 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 23/24
- 09:17 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 22/24
- 09:16 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 21/24
- 09:16 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 21/24
- 09:16 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 20/24
- 09:15 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 19/24
- 09:15 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 18/24
- 09:14 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 17/24
- 09:14 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 16/24
- 09:13 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 15/24
- 09:13 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 14/24
- 09:11 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 13/24
- 09:11 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 12/24
- 09:09 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 11/24
- 09:09 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 10/24
- 09:08 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 9/24
- 09:08 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 8/24
- 09:07 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 7/24
- 09:07 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 6/24
- 09:07 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 5/24
- 09:06 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 4/24
- 09:06 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 3/24
- 09:05 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 2/24
- 09:05 8.00 hours (Project progress work #486 (Closed): CYLC - Operation test confirmation/Specification creation)
- [Task] LAT - CYLC - Operation test confirmation/Specification creation 1/24
09 Sep 2024
- 16:46 8.00 hours (Project progress work #662 (Closed): PICS - Version upgrade development support handy terminal)
- Modify HT Software.
07 Sep 2024
- 16:55 8.00 hours (Project progress work #662 (Closed): PICS - Version upgrade development support handy terminal)
- Add Table Database HT Software.
06 Sep 2024
- 16:44 6.00 hours (Project progress work #662 (Closed): PICS - Version upgrade development support handy terminal)
- Add Table Database HT Software.