Parent project #3043: [PJ250094] SR Jig for HOWA PACKAGING (THAILAND) CO., LTD.
Project progress work #3172: [Installation&On-site support]
Parent project #6444: [PJ260022] SR Jig for HOWA PACKAGING (THAILAND) CO., LTD.
Project progress work #6445: [Requirement definition]

Status

In Progress
In Progress
In Progress
In Progress

Priority

Normal
Normal
Normal
Normal

Total estimated time

320.00
144.00
384.00
336.00

Total spent time

0.00
0.00
0.00
0.00

Updated

11 Mar 2026 11:13
11 Mar 2026 11:13
30 Mar 2026 14:09
30 Mar 2026 14:09
 
 
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
Tomas Tech All Project Management
 
HOWA PACKAGING (THAILAND) CO., LTD.
 
 
 
In Progress
Parent project #3043: [PJ250094] SR Jig for HOWA PACKAGING (THAILAND) CO., LTD.

Project: HOWA PACKAGING (THAILAND) CO., LTD.
Status: In Progress
Start date: 05 Jan 2025
Due date: 21 Jan 2026
Assignee: Nattapol Poeam
Priority: Normal
 
 
 
In Progress 100%
Project progress work #3172: [Installation&On-site support]

Project: HOWA PACKAGING (THAILAND) CO., LTD.
Status: In Progress
Start date: 05 Jan 2025
Due date: 21 Jan 2026
Assignee:
Priority: Normal
In Progress
In Progress 100%