11 Feb 2026

15:46 Project progress work #6445 (Closed): [Requirement definition]
Waraporn Promsopa
15:42 Project progress work #6445 (In Progress): [Requirement definition]
Waraporn Promsopa
15:45 Project progress work #6568 (Closed): [Requirement definition] Schedule Plan
Waraporn Promsopa
15:45 Project progress work #6568 (Closed): [Requirement definition] Schedule Plan
Waraporn Promsopa
14:44 Parent project #3043 (Closed): [PJ250094] SR Jig for HOWA PACKAGING (THAILAND) CO., LTD.
Waraporn Promsopa
14:44 Project progress work #3172 (Closed): [Installation&On-site support]
Waraporn Promsopa
14:42 Project progress work #3172 (In Progress): [Installation&On-site support]
Waraporn Promsopa
14:44 Project progress work #3179 (Closed): [Installation&On-site support] Go live
Waraporn Promsopa
14:44 Project progress work #3178 (Closed): [Installation&On-site support] Mechanical installation
Waraporn Promsopa
14:43 Project progress work #3178 (Interruption): [Installation&On-site support] Mechanical installation
Waraporn Promsopa
14:43 Project progress work #3177 (Closed): [Installation&On-site support] Electrical Installation
Waraporn Promsopa
14:43 Project progress work #3171 (Closed): [Coding]
Waraporn Promsopa
14:43 Project progress work #3176 (Closed): [Coding] Hardware pre-shipment confirmation
Waraporn Promsopa
14:43 Project progress work #3175 (Closed): [Coding] Wiring
Waraporn Promsopa
14:43 Project progress work #3174 (Closed): [Coding] Assembly
Waraporn Promsopa
10:25 Project progress work #6553 (Closed): [Internal design] Design and PR-request
Waraporn Promsopa
10:25 Project progress work #6553 (Closed): [Internal design] Design and PR-request
Waraporn Promsopa
09:59 Project progress work #3170 (Closed): [Internal Design]
Waraporn Promsopa
09:56 Project progress work #3170 (In Progress): [Internal Design]
Waraporn Promsopa
09:57 Project progress work #6545 (Closed): [Internal design] Dwg. Design & Assembly
Waraporn Promsopa
09:57 Project progress work #6545 (Closed): [Internal design] Dwg. Design & Assembly
Waraporn Promsopa

06 Feb 2026

09:34 Project progress work #6456 (Closed): [Installation&On-site support] User Testing & Trial
Waraporn Promsopa
09:33 Project progress work #6455 (Closed): [Installation&On-site support] BCR Config
Waraporn Promsopa
09:31 Project progress work #6454 (Closed): [Installation&On-site support] Hardware installation/Wirring
Waraporn Promsopa
09:29 Project progress work #6453 (Closed): [Coding] Assemble Jig Stand
Waraporn Promsopa
09:27 Project progress work #6452 (Closed): [Coding] Hardware pre-shipment confirmation
Waraporn Promsopa
09:25 Project progress work #6451 (Closed): [Coding] Hardware procurement
Waraporn Promsopa
09:22 Project progress work #6450 (Closed): [Internal Design] PR-Request
Waraporn Promsopa
09:22 Project progress work #6450 (Closed): [Internal Design] PR-Request
Waraporn Promsopa
09:20 Project progress work #6449 (Closed): [Internal Design] Jig Stand Drawing
Waraporn Promsopa
09:20 Project progress work #6449 (Closed): [Internal Design] Jig Stand Drawing
Waraporn Promsopa
09:11 Project progress work #6445 (Closed): [Requirement definition]
Waraporn Promsopa
08:56 Project progress work #6445 (Closed): [Requirement definition]
Waraporn Promsopa
09:01 Project progress work #6448 (Closed): [Installation&On-site support]
Waraporn Promsopa
09:00 Project progress work #6447 (Closed): [Coding]
Waraporn Promsopa
08:59 Project progress work #6446 (Closed): [Internal Design]
Waraporn Promsopa
08:52 Parent project #6444 (Closed): [PJ260022] SR Jig for HOWA PACKAGING (THAILAND) CO., LTD.
1 Mechanical cost
1-1 Sensor Jig Stand modification part 2 set
2 Electrical cost
2-1 Control Box modification pa...
Waraporn Promsopa
 