07 Feb 2024

17:40 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
develop pagasus Tanawan Wongsa-ard
17:28 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
develop web Tanawan Wongsa-ard

03 Feb 2024

15:31 8.00 hours (Project progress work #383 (Closed): Develop modify the master management module )
develop the application and customize by comment's issue Tanawan Wongsa-ard

31 Jan 2024

13:10 4.00 hours (Project progress work #16 (Closed): WMS Web Development )
fixed bug and internal testing Tanawan Wongsa-ard
13:09 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
fixed bug and internal testing Tanawan Wongsa-ard
13:08 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
Training and fixed bug at Ebisu site Tanawan Wongsa-ard
13:05 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
develop the application and customize by comment's issue Tanawan Wongsa-ard
 