Activity
From 01 May 2024 to 10 May 2024
10 May 2024
- 00:08 0.00 hour (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- 00:07 8.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- modify accept job function & test
- 00:06 8.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- modify accept job function
07 May 2024
- 16:58 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- Modify and test the web socket to support the ACCEPT request yes/no (continue) and multiple group joined
06 May 2024
- 16:41 4.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- Modify and test the web socket to support the ACCEPT request yes/no (continue)
- 16:40 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- Modify the web socket to support the ACCEPT request yes/no
04 May 2024
- 22:38 8.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- Installation&On-site support Day#5 and UAT 2/2
- 22:38 8.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- Installation&On-site support Day#4 and UAT 1/2
- 22:36 8.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- Installation&On-site support Day#3
- 22:36 8.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- Installation&On-site support Day#2
- 22:36 8.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- Installation&On-site support Day#1
- 22:33 0.00 hour (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- 22:31 8.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- Internal test smart watch with K.nack at office
- 22:30 8.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- Internal test smart watch at office
- 22:29 8.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- test & modify smart watch system with K.nack
- 22:28 8.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- test & modify smart watch system with K.nack
- 22:27 8.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- development connect to web socket and test
- 22:26 8.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- development connect to web socket
- 22:25 8.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- development count wait time and modify layout main page, acept job page.
- 22:24 8.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- development count wait time
- 22:21 8.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- modify acept job function
- 22:20 8.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- modify main activity of smart watch system
- 22:19 8.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- learn and understand program code.
- 22:18 8.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- Meeting with K.nack about the working concept of the smart watch. learn and understand program code.
02 May 2024
- 00:19 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- Fix for support join to the several groups
- 00:18 4.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- Fix for support join to the several groups
- 00:04 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- Installation day 5 and UAT 2/2
- 00:04 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- Installation day 4 and UAT 1/2
- 00:03 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- Installation day 3
- 00:03 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- Installation day 2
- 00:03 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- Installation day 1
- 00:02 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- Web socket coding
- 00:02 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- Web socket coding
- 00:01 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- Web socket coding
- 00:01 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- Web socket coding
- 00:01 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- Web socket coding
- 00:00 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- Web socket coding
01 May 2024
- 23:54 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- 23:53 8.00 hours (Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01)
- Database and system design