07 Nov 2025

15:33 Project progress work #2872 (In Progress): [Installation&On-site support]
Siriwilai Chaiwattanaphon
15:33 Project progress work #2871 (In Progress): [Coding]
Siriwilai Chaiwattanaphon
15:31 Project progress work #2870 (In Progress): [Internal Design]
Siriwilai Chaiwattanaphon
15:30 Project progress work #2869 (In Progress): [Requirement difinition]
Siriwilai Chaiwattanaphon
15:21 Parent project #2868 (In Progress): [PJ250080] Camera system modification for Thailand Add Alarm monitor

1. Software + Installation
1.1 Camera system for Thailand modification software and installation software [5 Day]...
Siriwilai Chaiwattanaphon

04 Nov 2025

16:52 Parent project #547 (Closed): [PJ220037]Camera barcode system Daifuku Makro for Thai
Siriwilai Chaiwattanaphon
16:52 Project progress work #802 (Closed): [Area3] Camera control system
Siriwilai Chaiwattanaphon
16:52 Project progress work #800 (Closed): [Area1] Camera control system
Siriwilai Chaiwattanaphon
16:52 Project progress work #1207 (Closed): [Installation&On-site support] Installation Camera and Stand
Siriwilai Chaiwattanaphon
16:52 Project progress work #1208 (Closed): [Installation&On-site support] FTP Test
Siriwilai Chaiwattanaphon
16:51 Project progress work #475 (Closed): [Area2]Camera control system
Siriwilai Chaiwattanaphon
16:51 Project progress work #66 (Closed): [Area3]Camera control system
Siriwilai Chaiwattanaphon
16:51 Project progress work #65 (Closed): [Area2]Camera control system
Siriwilai Chaiwattanaphon
16:51 Project progress work #64 (Closed): [Area1]Camera control system
Siriwilai Chaiwattanaphon
 