24 Dec 2023

15:31 5.00 hours (Problem-Bug #215 (Closed): Request verification of the data collection of machine)
Service and site to clear concept send and receive data from machine to PLC Tracability final line Nattapol Poeam
15:22 9.00 hours (Problem-Bug #215 (Closed): Request verification of the data collection of machine)
Service and site to clear concept send and receive data from machine to PLC Tracability final line Nattapol Poeam

23 Dec 2023

14:11 3.00 hours (Project progress work #334 (Closed): ATA meeting new year and greeting)
Meeitng and feedback Delta traceability system Ryo Nozaki

21 Dec 2023

16:56 8.00 hours (Project progress work #322 (Closed): Insert data part NG packageing at QC )
Finish Santi Srichankaew
 