Project

General

Profile

Activity

From 01 Aug 2024 to 10 Aug 2024

10 Aug 2024

17:40 Project progress work #590: [Coding] Warehouse management system handyterminal Java
- Design table and other. Taweesak Prumvised

09 Aug 2024

18:47 Project progress work #590: [Coding] Warehouse management system handyterminal Java
- Add outbound picking and shipping detail. Taweesak Prumvised

08 Aug 2024

18:46 Project progress work #590: [Coding] Warehouse management system handyterminal Java
- Meeting design sharing phase1.
- Add UI schedule of picking and shipping function.
Taweesak Prumvised
15:37 Project progress work #690 (Closed): [Coding] Warehouse management system PHP Linkage APIs
*Endpoint:*
* *Schedule Inbound*
status: testing in progress (8-Aug)
> > note: waiting for team Asuto confirm colu...
Thiraporn Amornsirinukorh
15:35 Project progress work #591 (Closed): [Coding] Warehouse management system handyterminal PHP
Ryo Nozaki
15:30 Project progress work #689 (Closed): [Coding] Warehouse management system PHP Linkage APIs
Create API for team Asuto data operations in ISEWAN project. Thiraporn Amornsirinukorh

02 Aug 2024

18:14 Project progress work #590: [Coding] Warehouse management system handyterminal Java
- Develop UI of outbound.
- Meeting with ASUTO about integration data.
Taweesak Prumvised
 

Also available in: Atom