Activity
From 18 Oct 2023 to 27 Oct 2023
25 Oct 2023
24 Oct 2023
- 18:59 Project progress work #21 (Close request): Handy terminal application system Development.
- 16:06 Project progress work #21 (Confirmation request): Handy terminal application system Development.
- Develop HT Software Finish krub.
19 Oct 2023
- 14:30 Project progress work #21: Handy terminal application system Development.
- Change due date to 10/24/2023 because I revise software Shodensha 10/20/2023 - 10/21/2023 krub.
- 09:20 Project progress work #21: Handy terminal application system Development.
- Develop HT send data to PLC.
- 11:59 Project progress work #110 (Closed): [On-site support]Support after cutover
- 11:59 Project progress work #109 (Closed): [On-site support]Support after cutover
- 09:49 Project progress work #38: Devolop and debug PLC Mitsubishi Q Series
- Deverlop PLC Keyencce test OK/NG data sendingnormal
next step
Deverlop to PLC Mitsubishi waiting demo PLC Mitsubi...