Activity
From 06 Jan 2026 to 15 Jan 2026
13 Jan 2026
- 15:00 Project progress work #4393 (New): [Installation&On-site support]
- 15:00 Project progress work #4392 (New): [Coding]
- 14:59 Project progress work #4391 (New): [Internal Design]
- 14:59 Project progress work #4390 (New): [Requirement definition]
- 14:37 Parent project #1517: [PJ250063] Two-point verification handheld terminal application
- 1.*Software*
Two-point verification handheld terminal application development fee
Inbound Feature: Item tag QR code... - 14:29 Project progress work #4389 (New): [Installation&On-site support]
- 14:29 Project progress work #4388 (New): [Coding]
- 14:28 Project progress work #4387 (New): [Internal Design]
- 14:28 Project progress work #4386 (New): [Requirement definition]
- 10:29 Parent project #3041 (Closed): [PJ250092] Hardware unit sets
Also available in: Atom