31 Jul 2024

16:11 8.00 hours (Project progress work #661 (Closed): [Colding] Handy terminal BT-A500 Java application)
-Internal Test, Create Package for install, Create user manual Priroj Neamjarn
16:10 8.00 hours (Project progress work #661 (Closed): [Colding] Handy terminal BT-A500 Java application)
-Internal Test, Create Package for install, Create user manual Priroj Neamjarn

30 Jul 2024

16:31 8.00 hours (Project progress work #661 (Closed): [Colding] Handy terminal BT-A500 Java application)
Import, Export to pc Priroj Neamjarn
16:31 8.00 hours (Project progress work #661 (Closed): [Colding] Handy terminal BT-A500 Java application)
Import, Export to pc Priroj Neamjarn

27 Jul 2024

16:33 8.00 hours (Project progress work #661 (Closed): [Colding] Handy terminal BT-A500 Java application)
Import, Export to pc Priroj Neamjarn
16:33 8.00 hours (Project progress work #661 (Closed): [Colding] Handy terminal BT-A500 Java application)
Import, Export to pc Priroj Neamjarn

26 Jul 2024

16:52 8.00 hours (Project progress work #661 (Closed): [Colding] Handy terminal BT-A500 Java application)
Import, Export to pc Priroj Neamjarn
16:51 8.00 hours (Project progress work #661 (Closed): [Colding] Handy terminal BT-A500 Java application)
Import, Export to pc Priroj Neamjarn

25 Jul 2024

16:49 8.00 hours (Project progress work #661 (Closed): [Colding] Handy terminal BT-A500 Java application)
coding work history screen, Import, Export to PC Priroj Neamjarn
16:49 8.00 hours (Project progress work #661 (Closed): [Colding] Handy terminal BT-A500 Java application)
coding work history screen, Import, Export to PC Priroj Neamjarn

24 Jul 2024

16:30 8.00 hours (Project progress work #661 (Closed): [Colding] Handy terminal BT-A500 Java application)
coding work history screen, Import, Export to PC Priroj Neamjarn
16:29 8.00 hours (Project progress work #661 (Closed): [Colding] Handy terminal BT-A500 Java application)
coding work history screen, Import, Export to PC Priroj Neamjarn

23 Jul 2024

16:44 8.00 hours (Project progress work #661 (Closed): [Colding] Handy terminal BT-A500 Java application)
coding pokayoke 3-points,work history screen, import-export to pc Priroj Neamjarn
16:44 8.00 hours (Project progress work #661 (Closed): [Colding] Handy terminal BT-A500 Java application)
coding pokayoke 3-points,work history screen, import-export to pc Priroj Neamjarn
 