Estimated time: 0.00 Spent time: 180.00

# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
3345 Project progress work New Normal [Installation&On-site support] 0.00 19 Dec 2025 10:51 Actions
3344 Project progress work New Normal [Coding] 0.00 19 Dec 2025 10:51 Actions
3343 Project progress work New Normal [Internal Design] 0.00 19 Dec 2025 10:50 Actions
3342 Project progress work New Normal [Requirement definition] 0.00 19 Dec 2025 10:50 Actions
3341 Parent project In Progress Normal [PJ250103] MOC packing system for AHT modification fee Convert to picking list Nattapol Poeam 0.00 0.00 19 Dec 2025 10:50 Actions
2996 Parent project In Progress Normal [PJ250088] MOC IoT system for wiring work AHT Nattapol Poeam 0.00 25 Nov 2025 11:49 Actions
1031 Project progress work Confirmation request Normal [Installation&On-site support] Nattapong Sukcharoen 40.00 25 Nov 2025 10:29 Actions
1030 Project progress work Confirmation request Normal [Coding] Nattapol Poeam 50.00 25 Nov 2025 10:28 Actions
1029 Project progress work Confirmation request Normal [Internal Design] Nattapong Sukcharoen 30.00 25 Nov 2025 10:27 Actions
1028 Project progress work Confirmation request Normal [Requirement definition] Nattapong Sukcharoen 60.00 25 Nov 2025 10:26 Actions
1027 Parent project In Progress Normal [PJ250017] Jig Pokayoke system for AH Brake (Thailand) Co., Ltd Nattapol Poeam 0.00 180.00 25 Nov 2025 10:29 Actions
    (1-11/11)