Parent project #3341: [PJ250103] MOC packing system for AHT modification fee Convert to picking list
Project progress work #3342: [Requirement definition]
Project progress work #3343: [Internal Design]
Project progress work #3345: [Installation&On-site support]
Parent project #1027: [PJ250017] Jig Pokayoke system for AH Brake (Thailand) Co., Ltd
Project progress work #1028: [Requirement definition]
Project progress work #1029: [Internal Design]
Project progress work #1031: [Installation&On-site support]
Parent project #2996: [PJ250088] MOC IoT system for wiring work AHT

Status

In Progress
New
New
New
New
In Progress
Confirmation request
Confirmation request
Confirmation request
Confirmation request
In Progress

Priority

Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal

Total estimated time

0.00
0.00

Total spent time

0.00
0.00
0.00
0.00
0.00
0.00

Updated

19 Dec 2025 10:50
19 Dec 2025 10:50
19 Dec 2025 10:50
19 Dec 2025 10:51
19 Dec 2025 10:51
25 Nov 2025 10:29
25 Nov 2025 10:26
25 Nov 2025 10:27
25 Nov 2025 10:28
25 Nov 2025 10:29
25 Nov 2025 11:49
 
 
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
Tomas Tech All Project Management
 
 
AH BRAKE (THAILAND) CO., LTD.
 
 
 
 
 
In Progress
Parent project #1027: [PJ250017] Jig Pokayoke system for AH Brake (Thailand) Co., Ltd

Project: AH BRAKE (THAILAND) CO., LTD.
Status: In Progress
Start date: 01 Jun 2025
Due date: 30 Jun 2025
Assignee: Nattapol Poeam
Priority: Normal
 
 
 
Confirmation request 100%
Project progress work #1028: [Requirement definition]

Project: AH BRAKE (THAILAND) CO., LTD.
Status: Confirmation request
Start date: 01 Jun 2025
Due date: 30 Jun 2025
Assignee: Nattapong Sukcharoen
Priority: Normal
 
 
 
Confirmation request 100%
Project progress work #1029: [Internal Design]

Project: AH BRAKE (THAILAND) CO., LTD.
Status: Confirmation request
Start date: 01 Jun 2025
Due date: 30 Jun 2025
Assignee: Nattapong Sukcharoen
Priority: Normal
 
 
 
Confirmation request 100%
Project progress work #1030: [Coding]

Project: AH BRAKE (THAILAND) CO., LTD.
Status: Confirmation request
Start date: 01 Jun 2025
Due date: 30 Jun 2025
Assignee: Nattapol Poeam
Priority: Normal
 
 
 
Confirmation request 100%
Project progress work #1031: [Installation&On-site support]

Project: AH BRAKE (THAILAND) CO., LTD.
Status: Confirmation request
Start date: 01 Jun 2025
Due date: 30 Jun 2025
Assignee: Nattapong Sukcharoen
Priority: Normal