Parent project #8248: [PJ260098] MT MOC traceability packing system for AH Brake for Line1 and Line2 Label
Parent project #8447: [PJ260109] Software modification Responding to changes in working hours
Project progress work #8448: [Requirement definition]
Project progress work #8449: [Internal Design]
Project progress work #8451: [Installation&On-site support]

Status

In Progress
In Progress
New
New
New
New

Priority

Normal
Normal
Normal
Normal
Normal
Normal

Total estimated time

0.00

Total spent time

0.00
0.00
0.00
0.00
0.00
0.00

Updated

26 May 2026 09:11
06 Jun 2026 15:57
06 Jun 2026 15:58
06 Jun 2026 15:59
06 Jun 2026 15:59
06 Jun 2026 15:59
 
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
Tomas Tech All Project Management
AH BRAKE (THAILAND) CO., LTD.

Also available in: PDF PNG