Activity
From 14 Mar 2025 to 23 Mar 2025
21 Mar 2025
- 18:02 8.00 hours (Project progress work #899 (Closed): MOC Monitoring system)
- Fixed web socket installation on site.
- 12:13 8.00 hours (Project progress work #899 (Closed): MOC Monitoring system)
- Fixed web socket installation on site.
18 Mar 2025
- 08:46 3.00 hours (Project progress work #899 (Closed): MOC Monitoring system)
- Fixed web socket installation on site.
15 Mar 2025
- 15:41 4.00 hours (Project progress work #904 (Closed): [Testing] Test and conduct the test report and user manual)
- Edit Layout Label and Fix bug problem
- 12:53 3.00 hours (Project progress work #904 (Closed): [Testing] Test and conduct the test report and user manual)
14 Mar 2025
- 17:23 8.00 hours (Project progress work #899 (Closed): MOC Monitoring system)
- Install web socket on ah site.