From 24 Nov 2024 to 03 Dec 2024

03 Dec 2024

11:11 Project progress work #842 (Closed): HW Onsite installation
1. Installation PLC Master
2. Installation HMI
3. Installation PC
4. Installation Table
5. Setup equipment
Nattapol Poeam
11:10 Project progress work #841 (Closed): Table installation
- Table installation and setup Nattapol Poeam
11:08 Project progress work #840 (Closed): Connect to machine
Connect CC-Link system to Machine
OP1
OP4
OP6
OP7.1
OP7.2
OP8
OP9
OP10.1
OP10.2
Nattapol Poeam
11:05 Project progress work #839 (Closed): Software external installation
- Installation Program PLC
- Installation Program C# Application
Nattapol Poeam
11:02 Project progress work #838 (Closed): Specification design
- Make specification for traceability AS004 Nattapol Poeam
10:59 Project progress work #837 (Closed): ME Assembly [ Table ]
- Assembly table Nattapol Poeam
10:58 Project progress work #836 (Closed): Wiring and assembly equipment panel box
- Wiring HMI Box
- Wiring Master control box
Nattapol Poeam
10:55 Project progress work #835 (Closed): EE Drawing deisgn
- Make drawing diagram
- Part list
- Make PO
Nattapol Poeam
 