22:09 Project progress work #436 (In Progress): [ On-site ] Installation shipping traceability system
[ To day ]
- Config AP
- Config Handy
- Wiring Power supply 24V to AP
[ Next Action ]
- Install AP
- Change DB
...
Nattapol Poeam
22:06 Project progress work #436 (Closed): [ On-site ] Installation shipping traceability system
Installation program
- Handy
- PC Packing
Installtion AP
- Final line MOC
Data base
- Change local DB to Server
Nattapol Poeam
 