06 Nov 2023
- 08:20 Project progress work #200 (Closed): Counter RH fucntion not operation
- Problem
-output PLC HARU machine not send signal.
Action
-check signal ladder plc haru machine found ladde...
03 Nov 2023
- 18:40 Sales support #164: IoT system for CNC line follow up
- Peeraphon of Keyence said that Fanuc PMC can load error massage by Ethernet I/P. But just only 8unit machine.
Other ... - 15:41 Sales support #164 (In Progress): IoT system for CNC line follow up
02 Nov 2023
- 08:54 Problem-Bug #174 (Closed): Data outstanding on table bekido [support on site ]
- PLC ladder check table bekido
31 Oct 2023