Project

General

Profile

Issues

Filters

Apply Clear

Estimated time: 426.00 Spent time: 524.50

# Project Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
6689 JTEKT ASIA PACIFIC CO.,LTD. Project progress work Closed Normal [Installation&On-site support] Install name plate Phatthadon Inthachot 8.00 0.00 19 Feb 2026 10:35 Actions
6688 JTEKT ASIA PACIFIC CO.,LTD. Project progress work Closed Normal [Installation&On-site support] Arrange Lan cables Phatthadon Inthachot 8.00 0.00 19 Feb 2026 10:34 Actions
1407 JTEKT ASIA PACIFIC CO.,LTD. Project progress work New Normal [Coding] Electric summary Phattarapong Kammee 0.00 19 Feb 2026 10:29 Actions
1406 JTEKT ASIA PACIFIC CO.,LTD. Project progress work New Normal [Coding] Sync data Phattarapong Kammee 0.00 19 Feb 2026 10:29 Actions
1405 JTEKT ASIA PACIFIC CO.,LTD. Project progress work New Normal [Coding] Manage target Phattarapong Kammee 0.00 19 Feb 2026 10:29 Actions
1404 JTEKT ASIA PACIFIC CO.,LTD. Project progress work New Normal [Coding] Manage peak rate Phattarapong Kammee 0.00 19 Feb 2026 10:29 Actions
1403 JTEKT ASIA PACIFIC CO.,LTD. Project progress work New Normal [Coding] Analysis Phattarapong Kammee 0.00 19 Feb 2026 10:29 Actions
1402 JTEKT ASIA PACIFIC CO.,LTD. Project progress work New Normal [Coding] Production monitoring Phattarapong Kammee 0.00 19 Feb 2026 10:29 Actions
1401 JTEKT ASIA PACIFIC CO.,LTD. Project progress work New Normal [Coding] Manage meter Phattarapong Kammee 0.00 19 Feb 2026 10:29 Actions
1400 JTEKT ASIA PACIFIC CO.,LTD. Project progress work New Normal [Coding] Factory monitoring Phattarapong Kammee 0.00 19 Feb 2026 10:29 Actions
1399 JTEKT ASIA PACIFIC CO.,LTD. Project progress work New Normal [Coding] Power meter 0.00 19 Feb 2026 10:29 Actions
1398 JTEKT ASIA PACIFIC CO.,LTD. Project progress work New Normal [Coding] Chiller Phattarapong Kammee 0.00 19 Feb 2026 10:29 Actions
1397 JTEKT ASIA PACIFIC CO.,LTD. Project progress work New Normal [Coding] Air flow Phattarapong Kammee 0.00 19 Feb 2026 10:29 Actions
1099 JTEKT ASIA PACIFIC CO.,LTD. Project progress work New Normal [Installation&On-site support] Nattapol Poeam 16.00 0.00 19 Feb 2026 10:32 Actions
1098 JTEKT ASIA PACIFIC CO.,LTD. Project progress work New Normal [Coding] Backend coding * hold, Waiting for shindengen Phattarapong Kammee 0.00 0.00 19 Feb 2026 10:29 Actions
1097 JTEKT ASIA PACIFIC CO.,LTD. Project progress work Closed Normal [Internal Design] Nattapol Poeam 0.00 19 Feb 2026 10:29 Actions
1096 JTEKT ASIA PACIFIC CO.,LTD. Project progress work Closed Normal [Requirement definition] Nattapol Poeam 0.00 19 Feb 2026 10:29 Actions
796 JTEKT ASIA PACIFIC CO.,LTD. Project progress work Closed Normal [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set Nattapong Sukcharoen 150.00 136.00 19 Feb 2026 10:29 Actions
737 JTEKT ASIA PACIFIC CO.,LTD. Project progress work Closed Normal [ Installation & Support ] Installation and wiring andon project Nattapong Sukcharoen 150.00 412.50 19 Feb 2026 10:29 Actions
720 JTEKT ASIA PACIFIC CO.,LTD. Project progress work Closed Normal Specification and system design Nattapol Poeam 100.00 64.00 19 Feb 2026 10:29 Actions
700 JTEKT ASIA PACIFIC CO.,LTD. Project progress work Closed Normal PR Electrical part Phatthadon Inthachot 80.00 16.00 19 Feb 2026 10:29 Actions
699 JTEKT ASIA PACIFIC CO.,LTD. Project progress work Closed Normal Electrical Diagram Phatthadon Inthachot 80.00 32.00 19 Feb 2026 10:29 Actions
    (1-22/22)

    Also available in: Atom CSV PDF