Estimated time: 200.00 Spent time: 0.00

# Project Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
8687 TOYOTA BOSHOKU GATEWAY (THAILAND) CO.,LTD. Project progress work Closed Normal [Coding] Develop Inbound, Stock, Label (Reprint) (Fontend & Backend), Stock Taking Functions (Frontend & Backend) Ronnagon Kongsuwan 24.00 0.00 24 Jun 2026 16:10 Actions
8686 TOYOTA BOSHOKU GATEWAY (THAILAND) CO.,LTD. Project progress work Closed Normal [Coding] Develop Temp_Inbound_Receive Integration for Offline and Online Receiving (Fontend & Backend) Ronnagon Kongsuwan 16.00 0.00 24 Jun 2026 16:10 Actions
8634 TOYOTA BOSHOKU GATEWAY (THAILAND) CO.,LTD. Project progress work Closed Normal [Coding] Develop Inbound Schedule And Inbound Schedule Detail Page (Fontend & Backend) Ronnagon Kongsuwan 16.00 0.00 19 Jun 2026 15:00 Actions
8633 TOYOTA BOSHOKU GATEWAY (THAILAND) CO.,LTD. Project progress work Closed Normal [Coding] Develop Import Purchase Order Page (Fontend & Backend) Ronnagon Kongsuwan 16.00 0.00 19 Jun 2026 15:00 Actions
8526 TOYOTA BOSHOKU GATEWAY (THAILAND) CO.,LTD. Project progress work Closed Normal [Requirement definition] Meeting to explain the overview of the designed WMS workflow for TBGT to the Vietnam Handy development team. Ronnagon Kongsuwan 8.00 0.00 12 Jun 2026 13:46 Actions
8525 TOYOTA BOSHOKU GATEWAY (THAILAND) CO.,LTD. Project progress work Closed Normal [Coding] Develop Master Data Management Pages (Item Master, Supplier Master, Location Master, Department Master, User Master, User Credential, Packing Standard) Ronnagon Kongsuwan 56.00 0.00 12 Jun 2026 13:44 Actions
8434 TOYOTA BOSHOKU GATEWAY (THAILAND) CO.,LTD. Project progress work Closed Normal [Requirement definition] Requirment summary meeting TBGT Mekkalar Sansiri 16.00 0.00 06 Jun 2026 14:53 Actions
8377 TOYOTA BOSHOKU GATEWAY (THAILAND) CO.,LTD. Project progress work Closed Normal [Internal Design] Prepare the system specification document. Ronnagon Kongsuwan 32.00 0.00 26 May 2026 15:48 Actions
8376 TOYOTA BOSHOKU GATEWAY (THAILAND) CO.,LTD. Project progress work Closed Normal [Requirement definition] Onsite requirement gathering with the customer for system specification design. Ronnagon Kongsuwan 16.00 0.00 26 May 2026 15:47 Actions
    (1-9/9)