Estimated time: 96.00 Spent time: 0.00

# Project Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
6857 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work Closed Normal [Installation&On-site support] install software and validation Suphawat Tinaso 24.00 0.00 11 Mar 2026 10:17 Actions
6856 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Modification software for support addition powermeter. Suphawat Tinaso 48.00 0.00 11 Mar 2026 10:16 Actions
6767 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work Closed Normal [Installation&On-site support] Installation Taweesak Suriyon 24.00 0.00 02 Mar 2026 13:19 Actions
6470 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work New Normal [Inatallation&On-site support] Go live Konlawat Saechee 0.00 06 Feb 2026 11:55 Actions
6469 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work New Normal [Installation&On-site support] Teaching for Go live Konlawat Saechee 0.00 06 Feb 2026 11:54 Actions
6468 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work New Normal [Inatallation&On-site support] Supports user feedback Konlawat Saechee 0.00 06 Feb 2026 11:53 Actions
6467 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work New Normal [Installation&On-site support] User Testing & Trial Konlawat Saechee 0.00 06 Feb 2026 11:51 Actions
6466 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work New Normal [Installation&On-site support] Teaching for UT Konlawat Saechee 0.00 06 Feb 2026 11:49 Actions
6465 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work New Normal [Installation&On-site support] Software installation (Web Application) Konlawat Saechee 0.00 06 Feb 2026 11:47 Actions
6464 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work New Normal [Installation&On-site support] Software installation (Application) Konlawat Saechee 0.00 06 Feb 2026 11:44 Actions
6463 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work New Normal [Installation&On-site support] Software installation (PLC) Konlawat Saechee 0.00 06 Feb 2026 11:42 Actions
6462 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work New Normal [Installation&On-site support] Power Meter installation Konlawat Saechee 0.00 06 Feb 2026 11:39 Actions
6461 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work New Normal [Coding] Hardware pre-shipment confirmation Konlawat Saechee 0.00 06 Feb 2026 11:36 Actions
6460 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work New Normal [Coding] Hardware procurement Konlawat Saechee 0.00 06 Feb 2026 11:35 Actions
6459 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work New Normal [Internal Design] System Design Konlawat Saechee 0.00 06 Feb 2026 11:34 Actions
6458 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work New Normal [Requirement definition] Requirements confirmation Konlawat Saechee 0.00 06 Feb 2026 11:24 Actions
6457 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work New Normal [Requirement definition] Kick-off meeting Konlawat Saechee 0.00 06 Feb 2026 11:22 Actions
5401 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work New Normal [Installation&On-site support] 48.00 0.00 11 Mar 2026 10:17 Actions
5400 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work New Normal [Coding] 48.00 0.00 11 Mar 2026 10:15 Actions
5399 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work New Normal [Internal Design] 0.00 0.00 06 Feb 2026 11:34 Actions
5398 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work New Normal [Requirement Definition] 0.00 0.00 06 Feb 2026 11:24 Actions
    (1-21/21)

    Also available in: Atom CSV PDF