Estimated time: 4105.00 Spent time: 1230.00

# Project Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
1229 Tomas Tech Co.,Ltd. Sales support New Normal Palletizer - Kao (Concept) Warit Chunlaka 80.00 0.00 22 Aug 2025 15:13 Actions
1228 Tomas Tech Co.,Ltd. Project progress work New Normal Palletizer - JCU (Concept) Warit Chunlaka 0.00 22 Aug 2025 14:45 Actions
1227 Tomas Tech Co.,Ltd. Project progress work Confirmation request Normal Estimate cost for Thai Yokorei (DAIFUKU) Warit Chunlaka 4.00 22 Aug 2025 15:01 Actions
1226 Tomas Tech Co.,Ltd. Project progress work Confirmation request Normal Estimate cost for DAIFUKU - PCG WET4 Warit Chunlaka 24.00 4.00 22 Aug 2025 14:58 Actions
1223 Tomas Tech Co.,Ltd. Project progress work New Normal [Requirement definition] Warit Chunlaka 104.00 8.00 22 Aug 2025 15:13 Actions
1216 Tomas Tech Co.,Ltd. Project progress work New Normal Appointment to Survey and Summary final data Nattawat Hannok 16.00 0.00 21 Aug 2025 15:29 Actions
1215 Tomas Tech Co.,Ltd. Project progress work New Normal Sent the list to Ryo san choose Nattawat Hannok 24.00 8.00 21 Aug 2025 15:29 Actions
1214 Tomas Tech Co.,Ltd. Project progress work New Normal Find WH and making list Nattawat Hannok 8.00 8.00 21 Aug 2025 15:19 Actions
1213 Tomas Tech Co.,Ltd. Project progress work New Normal Spec meeting Robot Palletizer (Kao) Warit Chunlaka 0.00 21 Aug 2025 14:44 Actions
1212 Tomas Tech Co.,Ltd. Project progress work New Normal Second hand Robot ( JCU - Palletizer ) Warit Chunlaka 0.00 21 Aug 2025 14:44 Actions
1211 Tomas Tech Co.,Ltd. Project progress work In Progress Normal Rental Warehouse Warit Chunlaka 32.00 16.00 21 Aug 2025 15:29 Actions
1210 Tomas Tech Co.,Ltd. Project progress work New Normal Standard for ME-Drawing Template / Parts list format Warit Chunlaka 104.00 16.00 21 Aug 2025 14:16 Actions
1209 Tomas Tech Co.,Ltd. Project progress work Confirmation request Normal Estimate cost for Thai Yokorei (DAIFUKU) Warit Chunlaka 8.00 4.00 22 Aug 2025 14:37 Actions
862 Tomas Tech Co.,Ltd. Project progress work In Progress Normal AHT CNC Montoring system Nattapol Poeam 60.00 16.00 24 Dec 2024 14:03 Actions
848 LOGISTICS ALLIANCE (THAILAND) CO.,LTD. Project progress work New Normal PICS - Support handy terminal Arunwit Isarapongporn 40.00 0.00 05 Dec 2024 18:44 Actions
806 Tomas Tech Co.,Ltd. Project progress work New Normal Estimate cost Phatthadon Inthachot 160.00 40.00 18 Nov 2024 00:42 Actions
798 Tomas Tech Co.,Ltd. Sales support New Normal Site survey customer for new project Phatthadon Inthachot 100.00 24.00 17 Nov 2024 21:16 Actions
736 Tomas Tech Co.,Ltd. Project progress work New Normal Installation Anti virus Norton 360 Arunwit Isarapongporn 24.00 8.00 01 Oct 2024 10:13 Actions
732 Tomas Tech Co.,Ltd. Sales support In Progress Normal [ Make concept & Summary cost ] Line operation monitoring Nattapol Poeam 50.00 4.00 25 Sep 2024 17:52 Actions
730 Tomas Tech Co.,Ltd. Sales support In Progress Normal [ Make concept & Summary cost ] Utility control monitoring and Production monitoring system Nattapol Poeam 50.00 28.00 23 Sep 2024 12:00 Actions
719 Tomas Tech Co.,Ltd. Sales support In Progress Normal Traceability new line for ADVICS Nattapol Poeam 100.00 48.00 16 Sep 2024 16:51 Actions
718 Tomas Tech Co.,Ltd. Project progress work In Progress Normal Machine operation monitoring for KAWASAKI Nattapol Poeam 100.00 56.00 16 Sep 2024 16:57 Actions
644 Tomas Tech Co.,Ltd. Project progress work In Progress Normal [ Task ] Internal management Nattapol Poeam 1000.00 44.00 11 Jul 2024 20:36 Actions
622 Tomas Tech Co.,Ltd. Project progress work In Progress Normal For internal meeting and other Soraya Norasing 100.00 172.00 30 Sep 2024 23:42 Actions
525 Tomas Tech Co.,Ltd. Project progress work New Normal Priroj Neamjarn Taking Day off January-December 2024 Priroj Neamjarn 80.00 0.00 04 May 2024 17:22 Actions
(1-25/43) Per page: 25, 50

Also available in: Atom CSV PDF