Estimated time: 472.00 Spent time: 1812.00

# Project Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
526 A.N.I. LOGISTICS, LTD. Problem-Bug Closed Normal [Installation&On-site support] CKD process management system phase3 for ANI Kittisak Isarapongporn 8.00 8.00 08 May 2024 16:42 Actions
468 A.N.I. LOGISTICS, LTD. Project progress work Closed Normal [Coding]Inner packing screen function C# Kittisak Isarapongporn 48.00 56.00 04 May 2024 15:11 Actions
467 A.N.I. LOGISTICS, LTD. Project progress work Closed Normal [Installation&On-site support] CKD process management system phase3 for ANI Ryo Nozaki 100.00 144.00 04 May 2024 15:11 Actions
466 A.N.I. LOGISTICS, LTD. Project progress work Closed Normal [Coding] PHP web function and web socket API Kittisak Isarapongporn 80.00 184.00 04 May 2024 15:11 Actions
350 A.N.I. LOGISTICS, LTD. Project progress work Closed Normal Meeting with ANI and discuss spec of phase03 Ryo Nozaki 8.00 8.00 04 May 2024 15:11 Actions
267 A.N.I. LOGISTICS, LTD. Project progress work Closed Normal [Requirement definition] CKD process management system phase3 Ryo Nozaki 40.00 6.00 04 May 2024 15:11 Actions
226 A.N.I. LOGISTICS, LTD. Project progress work Closed Normal CKD project requirement and document preparation Kittisak Isarapongporn 30.00 48.00 30 Oct 2025 09:04 Actions
225 A.N.I. LOGISTICS, LTD. Project progress work Closed Normal CCTV Installation Nattapol Poeam 100.00 60.00 30 Oct 2025 09:05 Actions
179 A.N.I. LOGISTICS, LTD. Sales support Closed Normal Join the meeting at on-site Kittisak Isarapongporn 4.00 4.00 04 May 2024 15:11 Actions
134 A.N.I. LOGISTICS, LTD. Project progress work Closed Normal [Installation&On-site support] CKD process management system phase3 for ANI Tanawan Wongsa-ard 0.00 30 Oct 2025 09:05 Actions
133 A.N.I. LOGISTICS, LTD. Project progress work Closed Normal [Installation&On-site support] CKD process management system phase3 for ANI Soraya Norasing 24.00 48.00 30 Oct 2025 09:11 Actions
132 A.N.I. LOGISTICS, LTD. Project progress work Closed Normal [Installation&On-site support] CKD process management system phase3 for ANI Kamol Anekchatnuntakool 0.00 30 Oct 2025 09:05 Actions
131 A.N.I. LOGISTICS, LTD. Project progress work Closed Normal [Coding]Android handy and tablet modification Java Soraya Norasing 194.00 24 Dec 2024 22:39 Actions
130 A.N.I. LOGISTICS, LTD. Project progress work Closed Normal [Coding]Inner packing screen function C# Kittisak Isarapongporn 1007.00 02 Mar 2025 11:42 Actions
129 A.N.I. LOGISTICS, LTD. Project progress work Interruption Normal [Coding]PHP Pegasus web function Tanawan Wongsa-ard 0.00 30 Oct 2025 09:03 Actions
128 A.N.I. LOGISTICS, LTD. Project progress work Closed Normal [Internal Design] DB and various functions, man-hour calculation Kittisak Isarapongporn 14.00 30 Oct 2025 09:04 Actions
62 A.N.I. LOGISTICS, LTD. Sales support Closed Normal CKD project phase3 Proposal activities + requirements definition Ryo Nozaki 30.00 31.00 04 May 2024 15:11 Actions
    (1-17/17)