4464 DAIFUKU (THAILAND) LTD. Project progress work New Normal [Installation&On-site support] Report preventive maintenance summary Phatthadon Inthachot 40.00 0.00 17 Jan 2026 10:29 Actions
4463 DAIFUKU (THAILAND) LTD. Project progress work New Normal [Installation&On-site support] Preventive maintenance Phatthadon Inthachot 16.00 0.00 17 Jan 2026 10:28 Actions
4462 DAIFUKU (THAILAND) LTD. Project progress work New Normal [Installation&On-site support] Phatthadon Inthachot 56.00 0.00 17 Jan 2026 10:29 Actions
4461 DAIFUKU (THAILAND) LTD. Project progress work Closed Normal [Coding] Phatthadon Inthachot 8.00 0.00 17 Jan 2026 10:27 Actions
4460 DAIFUKU (THAILAND) LTD. Project progress work Closed Normal [Internal Design] Phatthadon Inthachot 8.00 0.00 17 Jan 2026 10:27 Actions
4459 DAIFUKU (THAILAND) LTD. Project progress work Closed Normal [Requirement Definition] Phatthadon Inthachot 8.00 0.00 17 Jan 2026 10:27 Actions