8629 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] support Nopparat Talalux 112.00 0.00 19 Jun 2026 14:53 Actions
8628 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Installation&On-site support] on site install and support Nopparat Talalux 160.00 0.00 19 Jun 2026 14:51 Actions
8458 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Installation&On-site support] Install server test and software Worawit Khantamool 8.00 0.00 10 Jun 2026 13:12 Actions
8405 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Installation&On-site support] Install new program version Pattanasak Chaonchom 8.00 0.00 29 May 2026 15:28 Actions
8404 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Adjust program collect data for gas sensor Pattanasak Chaonchom 16.00 0.00 29 May 2026 15:27 Actions
8403 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Program C# , Web socket and API Pattanasak Chaonchom 88.00 0.00 29 May 2026 15:27 Actions
8372 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Creat Script API Automation Test for Unimocron project 16.00 0.00 26 May 2026 15:33 Actions
7336 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Implement api Web Unimicron Nopparat Talalux 80.00 0.00 30 Apr 2026 15:02 Actions
7333 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Implement api meter compare Nopparat Talalux 8.00 0.00 30 Apr 2026 15:01 Actions
7332 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Implement api Flow Summary dashboard Nopparat Talalux 12.00 0.00 30 Apr 2026 15:01 Actions
7320 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Creat Test Scenario for Test API Unimicron project Mekkalar Sansiri 8.00 0.00 30 Apr 2026 14:38 Actions
7193 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Installation&On-site support] Install server Phatthadon Inthachot 8.00 0.00 25 Apr 2026 13:37 Actions
7192 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Installation&On-site support] Safety Training Phatthadon Inthachot 8.00 0.00 25 Apr 2026 13:36 Actions
7191 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Internal Design] Order Sw. Hub Phatthadon Inthachot 24.00 0.00 25 Apr 2026 13:35 Actions
7188 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Installation&On-site support] Safety trainning Nattapong Sukcharoen 8.00 0.00 25 Apr 2026 13:04 Actions
7127 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Requirement definition] 'Safety training Worawit Khantamool 8.00 0.00 08 Apr 2026 10:44 Actions
7009 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Creat sharepoint for tag issue Unimicron project Mekkalar Sansiri 16.00 0.00 19 Mar 2026 11:46 Actions
7007 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Creat Test Scenario for Unimicron project Mekkalar Sansiri 16.00 0.00 19 Mar 2026 11:42 Actions
6960 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Fix PHP version issues Doan Trong Hieu 8.00 0.00 17 Mar 2026 15:07 Actions
6959 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Update Dashboard UI Doan Trong Hieu 72.00 0.00 17 Mar 2026 15:07 Actions
6929 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Setup code base for web Doan Trong Hieu 8.00 0.00 12 Mar 2026 13:30 Actions
6680 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Internal design] Purchase Requisition of Server and accessory (wait supplier) Phatthadon Inthachot 88.00 0.00 18 Feb 2026 14:08 Actions
6679 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Internal design] Rack layout and SCH Phatthadon Inthachot 40.00 0.00 18 Feb 2026 14:08 Actions
6678 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Installation&On-site support] Prepare unifrom for working at on-site unimicron Phatthadon Inthachot 8.00 0.00 18 Feb 2026 14:04 Actions
6626 UNIMICRON (THAILAND) CO., LTD. Project progress work Closed Normal [Installation&On-site support] Software installation Nattapol Poeam 0.00 10 Jun 2026 13:13 Actions