Project

General

Profile

Issues

Filters

Apply Clear

Estimated time: 905.60 Spent time: 0.00

# Project Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
7347 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Investigation of the MTTR Report Issue Thanthima Phaengkham 8.00 0.00 30 Apr 2026 15:33 Actions
7346 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Revised the downloaded Breakdown Log front-end to support Thai text display. Thanthima Phaengkham 8.00 0.00 30 Apr 2026 15:33 Actions
7345 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Tapping Program Version Validation. Thanthima Phaengkham 64.00 0.00 30 Apr 2026 15:33 Actions
7344 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Label Taping system modification - Taping label record Soraya Norasing 16.00 0.00 30 Apr 2026 15:28 Actions
7343 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Label Taping system modification - Check Machine Status Soraya Norasing 16.00 0.00 30 Apr 2026 15:28 Actions
7342 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Label Taping system modification - Taping Plan Soraya Norasing 40.00 0.00 30 Apr 2026 15:28 Actions
7005 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Regenerate All Historical Reports. Thanthima Phaengkham 8.00 0.00 19 Mar 2026 11:06 Actions
6963 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Fix bugs, Modify the UI and logic according to the new requirements in ASI_Test_Issue Nguyen Quang Truong 120.00 0.00 17 Mar 2026 16:02 Actions
6933 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Test app PJ250101 Nguyen Quang Truong 8.00 0.00 12 Mar 2026 13:41 Actions
6932 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Fix ASI_Test_Issue Nguyen Quang Truong 32.00 0.00 12 Mar 2026 13:38 Actions
6931 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Change UI Stop sceern & change logic insert data BE Nguyen Quang Truong 8.00 0.00 12 Mar 2026 13:38 Actions
6922 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Add process of AG AOI to all display Thiraporn Amornsirinukorh 56.00 0.00 12 Mar 2026 11:07 Actions
6713 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Fix:-TapingRankMaster import only partially succeeds (some records not saved) Thanthima Phaengkham 8.00 0.00 20 Feb 2026 10:08 Actions
6712 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Fix-Output Report Error Thanthima Phaengkham 8.00 0.00 20 Feb 2026 10:08 Actions
6666 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Modify and Add New Report Thanthima Phaengkham 56.00 0.00 18 Feb 2026 11:29 Actions
6665 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] New Master Thanthima Phaengkham 40.00 0.00 18 Feb 2026 11:29 Actions
6664 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Process control system modification Soraya Norasing 176.00 0.00 18 Feb 2026 11:08 Actions
6505 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Handy terminal test app Soraya Norasing 1.60 0.00 10 Feb 2026 13:03 Actions
6504 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Fix bugs check key Production/Process/Production_overview_id on DB Soraya Norasing 40.00 0.00 10 Feb 2026 13:01 Actions
6503 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Fix bugs after test handly terminal app. Soraya Norasing 32.00 0.00 10 Feb 2026 11:55 Actions
6502 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Test app, adjust FE and logic according to customer requirements. Soraya Norasing 40.00 0.00 10 Feb 2026 11:52 Actions
6501 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Config BE & test handy terminal app Soraya Norasing 8.00 0.00 10 Feb 2026 11:49 Actions
6500 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Test api Restful BE for FE handy terminal app Soraya Norasing 8.00 0.00 10 Feb 2026 11:48 Actions
6499 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Write BE PHP for FE handy terminal app Soraya Norasing 40.00 0.00 10 Feb 2026 11:37 Actions
6498 ASIAN STANLEY. INTERNATIONAL LIMITED. Project progress work Closed Normal [Coding] Machine Stop/Re-start Soraya Norasing 40.00 0.00 10 Feb 2026 11:37 Actions
(1-25/26) Per page: 25, 50

Also available in: Atom CSV PDF