3215 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work New Normal [Coding] Power on & I/O Check Taweesak Suriyon 8.00 0.00 13 Dec 2025 13:17 Actions
3214 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work Closed Normal [Coding] Assy & Wiring Taweesak Suriyon 16.00 0.00 13 Dec 2025 13:17 Actions
3213 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work Closed Normal [Coding] Check Equipment Taweesak Suriyon 16.00 0.00 11 Dec 2025 14:34 Actions
3212 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work Closed Normal [Coding] Order equipment Taweesak Suriyon 160.00 0.00 11 Dec 2025 14:34 Actions
3211 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work Closed Normal [Coding] PR Request Taweesak Suriyon 40.00 0.00 11 Dec 2025 14:34 Actions
3210 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work Closed Normal [Coding] Part list Taweesak Suriyon 24.00 0.00 11 Dec 2025 14:33 Actions
3209 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work Closed Normal [Coding] Drawing Design Taweesak Suriyon 24.00 0.00 11 Dec 2025 14:33 Actions
    (1-7/7)