Estimated time: 480.00 Spent time: 0.00

# Project Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
4440 AH BRAKE (THAILAND) CO., LTD. Project progress work New Normal [Coding] Config network for AHT Purinat Thongbaiyai 480.00 0.00 16 Jan 2026 11:28 Actions
4439 AH BRAKE (THAILAND) CO., LTD. Project progress work New Normal [Installation&On-site support] 0.00 16 Jan 2026 11:26 Actions
4438 AH BRAKE (THAILAND) CO., LTD. Project progress work New Normal [Coding] 480.00 0.00 16 Jan 2026 11:28 Actions
4437 AH BRAKE (THAILAND) CO., LTD. Project progress work New Normal [Internal Design] 0.00 16 Jan 2026 11:26 Actions
4436 AH BRAKE (THAILAND) CO., LTD. Project progress work New Normal [Requirement Definition] 0.00 16 Jan 2026 11:26 Actions
    (1-5/5)