3221 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work Closed Normal [Coding] Assy Nattawat Hannok 8.00 0.00 13 Dec 2025 13:18 Actions
3220 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work Closed Normal [Coding] Check equipment Nattawat Hannok 0.00 11 Dec 2025 15:13 Actions
3219 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work Closed Normal [Coding] Order equipment Nattawat Hannok 104.00 0.00 11 Dec 2025 15:13 Actions
3218 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work Closed Normal [Coding] PR Equipment Nattawat Hannok 24.00 0.00 11 Dec 2025 15:13 Actions
3217 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work Closed Normal [Coding] Part list Nattawat Hannok 24.00 0.00 11 Dec 2025 15:12 Actions
3216 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work Closed Normal [Coding] Drawing Design Nattawat Hannok 24.00 0.00 11 Dec 2025 15:12 Actions
3214 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work Closed Normal [Coding] Assy & Wiring Taweesak Suriyon 16.00 0.00 13 Dec 2025 13:17 Actions
3213 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work Closed Normal [Coding] Check Equipment Taweesak Suriyon 16.00 0.00 11 Dec 2025 14:34 Actions
3212 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work Closed Normal [Coding] Order equipment Taweesak Suriyon 160.00 0.00 11 Dec 2025 14:34 Actions
3211 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work Closed Normal [Coding] PR Request Taweesak Suriyon 40.00 0.00 11 Dec 2025 14:34 Actions
3210 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work Closed Normal [Coding] Part list Taweesak Suriyon 24.00 0.00 11 Dec 2025 14:33 Actions
3209 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work Closed Normal [Coding] Drawing Design Taweesak Suriyon 24.00 0.00 11 Dec 2025 14:33 Actions