6490 NIPPN (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Complete the data into NG report Thiraporn Amornsirinukorh 88.00 0.00 17 Mar 2026 16:04 Actions
6489 NIPPN (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] QA allow to not fill in the required fields Thiraporn Amornsirinukorh 88.00 0.00 17 Mar 2026 16:04 Actions
6488 NIPPN (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Add fields to input stop times Thiraporn Amornsirinukorh 48.00 0.00 10 Feb 2026 09:43 Actions
6487 NIPPN (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Adjust layout of special Kanban Thiraporn Amornsirinukorh 120.00 0.00 10 Feb 2026 09:41 Actions
6486 NIPPN (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Add manual selector of purchase order Thiraporn Amornsirinukorh 128.00 0.00 17 Mar 2026 16:04 Actions
6485 NIPPN (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Notify about missing parts master Thiraporn Amornsirinukorh 88.00 0.00 10 Feb 2026 09:37 Actions
6484 NIPPN (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Calculate order balance Thiraporn Amornsirinukorh 8.00 0.00 10 Feb 2026 09:34 Actions
6483 NIPPN (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Hide the canceled order show incorrectly Thiraporn Amornsirinukorh 8.00 0.00 10 Feb 2026 09:34 Actions
6482 NIPPN (THAILAND) CO., LTD. Project progress work Closed Normal [Coding] Orders' Kanban quantity mismatch Thiraporn Amornsirinukorh 24.00 0.00 10 Feb 2026 09:34 Actions