2953 THAI ASAHI DENSO CO., LTD Project progress work New Normal [Installation&On-site support] Production monitoring system UAT Nattapong Sukcharoen 40.00 0.00 18 Nov 2025 17:00 Actions
2952 THAI ASAHI DENSO CO., LTD Project progress work Closed Normal [Installation&On-site support] Utility system UAT Panupong Raksakit 32.00 0.00 18 Dec 2025 14:28 Actions
2951 THAI ASAHI DENSO CO., LTD Project progress work New Normal [Installation&On-site support] Air flow monitoring Panupong Raksakit 8.00 0.00 18 Nov 2025 16:56 Actions
2950 THAI ASAHI DENSO CO., LTD Project progress work New Normal [Installation&On-site support] Utility data monitoring Panupong Raksakit 16.00 0.00 18 Dec 2025 14:23 Actions
2949 THAI ASAHI DENSO CO., LTD Project progress work New Normal [Installation&On-site support] Utility monitoring Panupong Raksakit 16.00 0.00 18 Dec 2025 14:23 Actions
2948 THAI ASAHI DENSO CO., LTD Project progress work New Normal [Installation&On-site support] Calling system Nattapong Sukcharoen 8.00 0.00 18 Nov 2025 16:41 Actions
2947 THAI ASAHI DENSO CO., LTD Project progress work New Normal [Installation&On-site support] Alarm monitoring Nattapong Sukcharoen 16.00 0.00 18 Nov 2025 16:40 Actions
2946 THAI ASAHI DENSO CO., LTD Project progress work Closed Normal [Installation&On-site support] 3D Production monitoring Nattapong Sukcharoen 16.00 0.00 18 Dec 2025 14:33 Actions
2945 THAI ASAHI DENSO CO., LTD Project progress work Closed Normal [Installation&On-site support] 3D Facility Monitoring Nattapong Sukcharoen 16.00 0.00 18 Dec 2025 14:32 Actions
2944 THAI ASAHI DENSO CO., LTD Project progress work Closed Normal [Installation&On-site support] Production monitoring System / OEE / Report Nattapong Sukcharoen 16.00 0.00 18 Dec 2025 14:33 Actions
2943 THAI ASAHI DENSO CO., LTD Project progress work Closed Normal [Installation&On-site support] ANDON System / Production Overview Nattapong Sukcharoen 16.00 0.00 18 Dec 2025 14:32 Actions
2942 THAI ASAHI DENSO CO., LTD Project progress work Closed Normal [Installation&On-site support] PLC Production group 4 [ 15 Machine ] Nattapong Sukcharoen 32.00 0.00 18 Dec 2025 14:31 Actions
2941 THAI ASAHI DENSO CO., LTD Project progress work Closed Normal [Installation&On-site support] PLC Production group 3 [ 15 Machine ] Nattapong Sukcharoen 32.00 0.00 18 Dec 2025 14:30 Actions
2940 THAI ASAHI DENSO CO., LTD Project progress work Closed Normal [Installation&On-site support] PLC Production group 2 [ 15 Machine ] Nattapong Sukcharoen 40.00 0.00 18 Dec 2025 14:29 Actions
2939 THAI ASAHI DENSO CO., LTD Project progress work Closed Normal [Installation&On-site support] PLC Production group 1 [ 15 Machine ] Nattapong Sukcharoen 40.00 0.00 18 Dec 2025 14:29 Actions
2938 THAI ASAHI DENSO CO., LTD Project progress work Closed Normal [Installation&On-site support] PLC Production configuration & UAT Line 9/7 Nattapong Sukcharoen 16.00 0.00 18 Dec 2025 14:29 Actions
2937 THAI ASAHI DENSO CO., LTD Project progress work Closed Normal [Installation&On-site support] PLC Main system installation Nattapong Sukcharoen 24.00 0.00 18 Dec 2025 14:29 Actions
2936 THAI ASAHI DENSO CO., LTD Project progress work Closed Normal [Installation&On-site support] Configuration / Setup master Pattanasak Chaonchom 8.00 0.00 18 Dec 2025 14:29 Actions
2935 THAI ASAHI DENSO CO., LTD Project progress work Closed Normal [Installation&On-site support] Server software installation Pattanasak Chaonchom 8.00 0.00 18 Dec 2025 14:29 Actions
2934 THAI ASAHI DENSO CO., LTD Project progress work New Normal [Installation&On-site support] UAT 72.00 0.00 18 Dec 2025 14:23 Actions
2933 THAI ASAHI DENSO CO., LTD Project progress work New Normal [Installation&On-site support] SIT Utility system 40.00 0.00 18 Dec 2025 14:23 Actions
2932 THAI ASAHI DENSO CO., LTD Project progress work New Normal [Installation&On-site support] SIT Production system 88.00 0.00 18 Dec 2025 14:24 Actions
2931 THAI ASAHI DENSO CO., LTD Project progress work Closed Normal [Installation&On-site support] Production software installation 200.00 0.00 18 Dec 2025 14:31 Actions
2930 THAI ASAHI DENSO CO., LTD Project progress work Closed Normal [Installation&On-site support] Air jet fan monitoring & Control Panupong Raksakit 8.00 0.00 18 Dec 2025 14:30 Actions
2929 THAI ASAHI DENSO CO., LTD Project progress work Closed Normal [Installation&On-site support] Blower exhaust 5 monitoring & Control Panupong Raksakit 16.00 0.00 18 Dec 2025 14:30 Actions
(1-25/32) Per page: 25, 50