3376 A.N.I. LOGISTICS, LTD. Project progress work New Normal [Installation&On-site support] Go live 8.00 0.00 23 Dec 2025 16:17 Actions
3375 A.N.I. LOGISTICS, LTD. Project progress work New Normal [Installation&Onsite support] Monitoring program install 0.00 23 Dec 2025 16:07 Actions
3374 A.N.I. LOGISTICS, LTD. Project progress work New Normal [Installation&Onsite support] On-line program modification 24.00 0.00 23 Dec 2025 16:06 Actions
3373 A.N.I. LOGISTICS, LTD. Project progress work New Normal [Installation&On-site support] Pre-Go live for 1line 8.00 0.00 23 Dec 2025 16:05 Actions
3372 A.N.I. LOGISTICS, LTD. Project progress work New Normal [Installation&On-site support] Teaching for Go live 80.00 0.00 23 Dec 2025 16:04 Actions
3366 A.N.I. LOGISTICS, LTD. Project progress work New Normal [Installation&On-site support] Supports user feedback 120.00 0.00 23 Dec 2025 15:59 Actions
3365 A.N.I. LOGISTICS, LTD. Project progress work New Normal [Installation&On-site support] User Testing & Trial (WC) 40.00 0.00 23 Dec 2025 14:27 Actions
3364 A.N.I. LOGISTICS, LTD. Project progress work New Normal [Installation&On-site support] SD card installation 8units 8.00 0.00 23 Dec 2025 14:19 Actions