3194 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work New Normal [Coding] Boring machine [ Zone 1 ] Purinat Thongbaiyai 40.00 0.00 22 Jan 2026 11:14 Actions
3193 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work New Normal [Coding] Machine data prepare Nattapong Sukcharoen 400.00 0.00 22 Jan 2026 11:48 Actions
3192 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work New Normal [Coding] SIT Phattarapong Kammee 40.00 0.00 22 Jan 2026 11:14 Actions
3190 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work New Normal [Coding] Web application Phattarapong Kammee 40.00 0.00 22 Jan 2026 13:10 Actions
3189 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work New Normal [Coding] SIT Suphawat Tinaso 40.00 0.00 17 Jan 2026 13:42 Actions
3188 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work New Normal [Coding] Development and modification Suphawat Tinaso 0.00 22 Jan 2026 11:16 Actions
3187 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work New Normal [Coding] Windows application & Database Suphawat Tinaso 120.00 0.00 22 Jan 2026 11:16 Actions
3186 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work New Normal [Coding] SIT Sermsak Prowee 40.00 0.00 22 Jan 2026 10:57 Actions
3185 FTS AUTOMOTIVE (THAILAND) CO.,LTD Project progress work New Normal [Coding] Development Sermsak Prowee 120.00 0.00 22 Jan 2026 10:57 Actions
3182 NIPPN (THAILAND) CO., LTD. Project progress work In Progress Normal [Installation&IOn-site support] Surasak Atchanawat 0.00 08 Jan 2026 16:49 Actions
3181 NIPPN (THAILAND) CO., LTD. Project progress work In Progress Normal [Installation&On-site support] Supatnchai Hempolchom 0.00 08 Jan 2026 16:50 Actions
3180 NIPPN (THAILAND) CO., LTD. Project progress work In Progress Normal [Installation&On-site support] Nattikorn Srisadet 0.00 08 Jan 2026 16:49 Actions
3179 HOWA PACKAGING (THAILAND) CO., LTD. Project progress work New Normal [Installation&On-site support] Go live Taweesak Suriyon 40.00 0.00 11 Dec 2025 09:33 Actions
3178 HOWA PACKAGING (THAILAND) CO., LTD. Project progress work New Normal [Installation&On-site support] Mechanical installation Nattawat Hannok 16.00 0.00 11 Dec 2025 09:32 Actions
3177 HOWA PACKAGING (THAILAND) CO., LTD. Project progress work New Normal [Installation&On-site support] Electrical Installation Taweesak Suriyon 16.00 0.00 11 Dec 2025 09:31 Actions
3176 HOWA PACKAGING (THAILAND) CO., LTD. Project progress work New Normal [Coding] Hardware pre-shipment confirmation Taweesak Suriyon 16.00 0.00 11 Dec 2025 09:29 Actions
3175 HOWA PACKAGING (THAILAND) CO., LTD. Project progress work New Normal [Coding] Wiring Taweesak Suriyon 16.00 0.00 11 Dec 2025 09:29 Actions
3174 HOWA PACKAGING (THAILAND) CO., LTD. Project progress work New Normal [Coding] Assembly Nattawat Hannok 16.00 0.00 11 Dec 2025 09:28 Actions
3172 HOWA PACKAGING (THAILAND) CO., LTD. Project progress work New Normal [Installation&On-site support] 128.00 0.00 11 Dec 2025 09:35 Actions
3171 HOWA PACKAGING (THAILAND) CO., LTD. Project progress work In Progress Normal [Coding] 112.00 0.00 11 Dec 2025 09:35 Actions
3167 MITSUI PRECISION THAI CO., LTD. Project progress work New Normal [Coding] Printer Setting Soraya Norasing 8.00 0.00 30 Jan 2026 14:37 Actions
3164 MITSUI PRECISION THAI CO., LTD. Project progress work New Normal [Coding] Outbound Crusher Soraya Norasing 24.00 0.00 30 Jan 2026 14:55 Actions
3159 MITSUI PRECISION THAI CO., LTD. Project progress work New Normal [Coding] QC Check Soraya Norasing 40.00 0.00 29 Jan 2026 13:50 Actions
3153 MITSUI PRECISION THAI CO., LTD. Project progress work New Normal [Coding] Soraya Norasing 336.00 0.00 30 Jan 2026 14:55 Actions
3152 A.N.I. LOGISTICS, LTD. Project progress work New Normal [Installation&On-site support] 0.00 09 Dec 2025 08:54 Actions