Estimated time: 8378.00 Spent time: 4682.50

# Project Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
883 AH BRAKE (THAILAND) CO., LTD. Project progress work Closed Normal [ Installation & On-site support] Software installation and configuration Line CY#2,MT#2 Purinat Thongbaiyai 200.00 0.00 04 Nov 2025 16:09 Actions
882 AH BRAKE (THAILAND) CO., LTD. Project progress work Closed Normal [ Installation & On-site support] Software installation and configuration Line CY#1,MT#1 Nattapong Sukcharoen 200.00 0.00 04 Nov 2025 16:09 Actions
881 AH BRAKE (THAILAND) CO., LTD. Project progress work Closed Normal [ Connect ] Connect to machine IoT CNC Line CY#2,MT#2 Purinat Thongbaiyai 200.00 0.00 04 Nov 2025 16:09 Actions
880 AH BRAKE (THAILAND) CO., LTD. Project progress work Closed Normal [ Connect ] Connect to machine IoT CNC Line CY#1,MT#1 Nattapong Sukcharoen 200.00 0.00 04 Nov 2025 16:09 Actions
879 AH BRAKE (THAILAND) CO., LTD. Project progress work Closed Normal [ Installation & On-site support ] Hardware installation Nattapong Sukcharoen 350.00 0.00 04 Nov 2025 16:09 Actions
858 NTN Manufacturing(Thailand) Co., Ltd. Project progress work Closed Normal [ Installation & On-site support] Program PLC Installation Pintong Konlawat Saechee 60.00 0.00 18 Nov 2025 13:55 Actions
857 NTN Manufacturing(Thailand) Co., Ltd. Project progress work Closed Normal [ Installation & On-site support] Program PLC Installation Soi6 Konlawat Saechee 60.00 0.00 18 Nov 2025 13:55 Actions
856 NTN Manufacturing(Thailand) Co., Ltd. Project progress work Closed Normal [ Installation & On-site support] Program PLC Installation Soi3 Konlawat Saechee 60.00 0.00 18 Nov 2025 13:54 Actions
855 NTN Manufacturing(Thailand) Co., Ltd. Project progress work Closed Normal [ Installation & On-site support] Control box installation #Pintong Phatthadon Inthachot 100.00 0.00 18 Nov 2025 13:52 Actions
854 NTN Manufacturing(Thailand) Co., Ltd. Project progress work Closed Normal [ Installation & On-site support] Control box installation #Soi6 Phatthadon Inthachot 100.00 0.00 18 Nov 2025 13:52 Actions
853 NTN Manufacturing(Thailand) Co., Ltd. Project progress work Closed Normal [ Installation & On-site support] Control box installation #Soi3 Phatthadon Inthachot 100.00 0.00 18 Nov 2025 13:52 Actions
852 NTN Manufacturing(Thailand) Co., Ltd. Project progress work Closed Normal [ Installation & On-site support] Software installation PLC Konlawat Saechee 300.00 0.00 18 Nov 2025 13:55 Actions
851 NTN Manufacturing(Thailand) Co., Ltd. Project progress work Closed Normal [ Coding ] Program development PLC Konlawat Saechee 160.00 8.00 18 Nov 2025 13:54 Actions
850 NTN Manufacturing(Thailand) Co., Ltd. Project progress work Closed Normal Power Meter Parameter check Konlawat Saechee 60.00 4.00 18 Nov 2025 13:57 Actions
849 NTN Manufacturing(Thailand) Co., Ltd. Project progress work Closed Normal EE Drawing deisgn Phatthadon Inthachot 60.00 56.00 18 Nov 2025 13:52 Actions
842 ADVICS Manufacturing(Thailand)Co.,Ltd. Project progress work Closed Normal HW Onsite installation Nattapong Sukcharoen 100.00 0.00 04 Nov 2025 16:14 Actions
841 ADVICS Manufacturing(Thailand)Co.,Ltd. Project progress work Closed Normal Table installation Konlawat Saechee 60.00 8.00 02 Mar 2025 11:42 Actions
840 ADVICS Manufacturing(Thailand)Co.,Ltd. Project progress work Closed Normal Connect to machine Nattapong Sukcharoen 80.00 0.00 04 Nov 2025 16:14 Actions
839 ADVICS Manufacturing(Thailand)Co.,Ltd. Project progress work Closed Normal Software external installation Nattapol Poeam 100.00 0.00 04 Nov 2025 16:14 Actions
838 ADVICS Manufacturing(Thailand)Co.,Ltd. Project progress work Closed Normal Specification design Nattapol Poeam 50.00 0.00 04 Nov 2025 16:14 Actions
837 ADVICS Manufacturing(Thailand)Co.,Ltd. Project progress work Closed Normal ME Assembly [ Table ] Konlawat Saechee 60.00 8.00 02 Mar 2025 11:42 Actions
836 ADVICS Manufacturing(Thailand)Co.,Ltd. Project progress work Closed Normal Wiring and assembly equipment panel box Phatthadon Inthachot 60.00 0.00 04 Nov 2025 16:13 Actions
835 ADVICS Manufacturing(Thailand)Co.,Ltd. Project progress work Closed Normal EE Drawing deisgn Phatthadon Inthachot 60.00 48.00 04 Nov 2025 16:13 Actions
729 AH BRAKE (THAILAND) CO., LTD. Project progress work Closed Normal [ Installation & On-site support] Hardware installation for IoT Loss analysis MOC and Packing process Line 1,2 Phatthadon Inthachot 200.00 179.50 04 Nov 2025 16:06 Actions
720 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work Closed Normal Specification and system design Nattapol Poeam 100.00 64.00 02 Mar 2025 11:42 Actions
(1-25/93) Per page: 25, 50, 100

Also available in: Atom CSV PDF