36

1

2

3

4

5

6

7

37

8

9

10

11

12

NTPT COMPANY LIMITED. - Project progress work #1145: [Coding] Project progress work #1145: [Coding]

Project: NTPT COMPANY LIMITED.
Status: New
Start date: 16 Jan 2024
Due date: 12 Sep 2024
Assignee: Kittisak Isarapongporn
Priority: Normal
NTPT COMPANY LIMITED. - Project progress work #1144: [Internal Design] Project progress work #1144: [Internal Design]

Project: NTPT COMPANY LIMITED.
Status: New
Start date: 16 Jan 2024
Due date: 12 Sep 2024
Assignee: Kittisak Isarapongporn
Priority: Normal

13

14

38

15

16

TOMAS TECH CO., LTD. - Sales support #722: MCCT Make concept and summa... Sales support #722: MCCT Make concept and summary cost

Project: TOMAS TECH CO., LTD.
Status: In Progress
Start date: 16 Sep 2024
Due date: 30 Sep 2024
Assignee: Nattapol Poeam
Priority: Normal
TOMAS TECH CO., LTD. - Project progress work #718: Machine operation monitorin... Project progress work #718: Machine operation monitoring for KAWASAKI

Project: TOMAS TECH CO., LTD.
Status: In Progress
Start date: 16 Sep 2024
Due date: 31 Oct 2024
Assignee: Nattapol Poeam
Priority: Normal

17

FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #764: FTP DATA LOGGING Project progress work #764: FTP DATA LOGGING

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 17 Sep 2024
Due date: 30 Nov 2024
Assignee: Panupong Raksakit
Priority: Normal
JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. - Project progress work #763: ANDON DASHBOARD DESIGN AND ... Project progress work #763: ANDON DASHBOARD DESIGN AND PROGRAMMING

Project: JTEKT AUTOMOTIVE (THAILAND) CO.,LTD.
Status: New
Start date: 17 Sep 2024
Due date: 30 Nov 2024
Assignee: Panupong Raksakit
Priority: Normal

18

19

20

21

39

22

23

TOMAS TECH CO., LTD. - Project progress work #736: Installation Anti virus Nor... Project progress work #736: Installation Anti virus Norton 360

Project: TOMAS TECH CO., LTD.
Status: New
Start date: 23 Sep 2024
Due date: 04 Oct 2024
Assignee: Arunwit Isarapongporn
Priority: Normal
TOMAS TECH CO., LTD. - Sales support #730: [ Make concept & Summary co... Sales support #730: [ Make concept & Summary cost ] Utility control monitoring and Production monitoring system

Project: TOMAS TECH CO., LTD.
Status: In Progress
Start date: 23 Sep 2024
Due date: 31 Oct 2024
Assignee: Nattapol Poeam
Priority: Normal

24

THAI METALTECH CO., LTD. - Sales support #731: installation&Training Sales support #731: installation&Training

Project: THAI METALTECH CO., LTD.
Status: In Progress
Start date: 24 Sep 2024
Due date: 25 Sep 2024
Assignee:
Priority: Normal

25

THAI METALTECH CO., LTD. - Sales support #731: installation&Training Sales support #731: installation&Training

Project: THAI METALTECH CO., LTD.
Status: In Progress
Start date: 24 Sep 2024
Due date: 25 Sep 2024
Assignee:
Priority: Normal
TOMAS TECH CO., LTD. - Sales support #732: [ Make concept & Summary co... Sales support #732: [ Make concept & Summary cost ] Line operation monitoring

Project: TOMAS TECH CO., LTD.
Status: In Progress
Start date: 25 Sep 2024
Due date: 31 Oct 2024
Assignee: Nattapol Poeam
Priority: Normal

26

27

28

40

29

30

NTPT COMPANY LIMITED. - Project progress work #1146: [Installation&On-site support] Project progress work #1146: [Installation&On-site support]

Project: NTPT COMPANY LIMITED.
Status: New
Start date: 16 Jan 2024
Due date: 30 Sep 2024
Assignee: Kittisak Isarapongporn
Priority: Normal
NTPT COMPANY LIMITED. - Project progress work #1143: [Requirement definition] Project progress work #1143: [Requirement definition]

Project: NTPT COMPANY LIMITED.
Status: New
Start date: 16 Jan 2024
Due date: 30 Sep 2024
Assignee: Kittisak Isarapongporn
Priority: Normal
TOMAS TECH CO., LTD. - Sales support #722: MCCT Make concept and summa... Sales support #722: MCCT Make concept and summary cost

Project: TOMAS TECH CO., LTD.
Status: In Progress
Start date: 16 Sep 2024
Due date: 30 Sep 2024
Assignee: Nattapol Poeam
Priority: Normal
NTPT COMPANY LIMITED. - Project progress work #665: [Setting] Link with i-Repor... Project progress work #665: [Setting] Link with i-Reporter and Asprova

Project: NTPT COMPANY LIMITED.
Status: New
Start date: 14 Jul 2024
Due date: 30 Sep 2024
Assignee: Arunwit Isarapongporn
Priority: Normal
NTPT COMPANY LIMITED. - Parent project #537: [PJ240010]Production planni... Parent project #537: [PJ240010]Production planning system APS 500,000 work

Project: NTPT COMPANY LIMITED.
Status: New
Start date: 16 Jan 2024
Due date: 30 Sep 2024
Assignee: Ryo Nozaki
Priority: Normal

1

A.N.I. LOGISTICS, LTD. - Parent project #1022: [PJ250028] IKD Management S... Parent project #1022: [PJ250028] IKD Management System for A.N.I.

Project: A.N.I. LOGISTICS, LTD.
Status: In Progress
Start date: 01 Oct 2024
Due date: 27 Dec 2025
Assignee: Kittisak Isarapongporn
Priority: Normal
JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. - Project progress work #728: [ Installation & On-site su... Project progress work #728: [ Installation & On-site support] Software installation for IoT Loss analysis MOC Line 1,2

Project: JTEKT AUTOMOTIVE (THAILAND) CO.,LTD.
Status: New
Start date: 01 Oct 2024
Due date: 31 Dec 2024
Assignee: Konlawat Saechee
Priority: Normal

2

3

TOMAS TECH CO., LTD. - Project progress work #740: [Development] Mobile androi... Project progress work #740: [Development] Mobile android device and api development.

Project: TOMAS TECH CO., LTD.
Status: In Progress
Start date: 03 Oct 2024
Due date: 25 Oct 2024
Assignee: Taweesak Prumvised
Priority: Normal
TOMAS TECH CO., LTD. - Parent project #726: [PJ*****] Mobile project fo... Parent project #726: [PJ*****] Mobile project for NFC smart card and calling system for mobile

Project: TOMAS TECH CO., LTD.
Status: In Progress
Start date: 03 Oct 2024
Due date: 14 Dec 2024
Assignee: Ryo Nozaki
Priority: Normal

4

TOMAS TECH CO., LTD. - Project progress work #736: Installation Anti virus Nor... Project progress work #736: Installation Anti virus Norton 360

Project: TOMAS TECH CO., LTD.
Status: New
Start date: 23 Sep 2024
Due date: 04 Oct 2024
Assignee: Arunwit Isarapongporn
Priority: Normal