open[PJ260104] Robot Palletizer JCU (THAILAND) CO., LTD
Updated by Waraporn Promsopa 4 days ago
1 Standard equipment cost
1-1 Finish good Product Storage (4 Tiered) **Warranty 5years Qty 1 set
1-2 Raw Material Storage (4 Tiered) **Warranty 5years Qty 1 set
1-3 Hazardous Material Store1 (3 Tiered) **Warranty 5years Qty 1 set
1-4 Hazardous Material Store2 (3 Tiered) **Warranty 5years Qty 1 set
1-5 Hazardous Material Store3 (3 Tiered) **Warranty 5years Qty 1 set
1-6 Transport and Install (Shelf) Qty 1 set
1-7 Nachi : LP180 (Incuded option) Qty 2 set
1-8 PLC : Keyence [KV-8000 ] [Filling Line] Qty 1 set
1-9 PLC : Keyence [KV-8000 ] [Palletizer Line] Qty 1 set
2 Robot Gripper cost
2-1 Air Gripper Unit + Displacment Sensor 2 sets Qty 2 set
3 Electrical cost
3-1 Main Control Panel [Filling Zone] Qty 1 set
3-2 Remote Contro Box / Field Wiring (Filling Zone) Qty 1 set
3-3 Main Control Panel [Palletizer] Qty 1 set
3-4 Remote Contro Box / Field Wiring (Palletizer Zone) Qty 1 set
4 Electrical labore cost
4-1 Inside : Drawing Design 1 job
4-2 Inside : Wiring and Assy 1 job
4-3 Supplier man/hour inside : Wiring and Assy 1 job
4-4 Supplier man/hour inside : Dismantle Unit and Packing 1 job
4-5 Outside : Wiring and Installation 1 job
4-6 Outside : Support I/O Check 1 job
4-7 Supplier man/hour outside : Wiring and Installation 1 job
5 Mechanical cost
5-1 Roller Conveyor unit / Chain diverter unit Qty 1 set
5-2 Top Chain Conveyor unit / Chain diverter unit Qty 1 set
5-3 Robot unit Qty 2 set
5-4 Auto Pallet Stock & Buffer stock Qty 1 set
5-5 FRL Uni Qty 1 set
5-6 Electrical Bracket Qty 1 job
5-7 Fence & duct Qty 1 job
5-8 Belt Conveyor unit Qty 1 job
5-9 Ladder unit Qty 1 job
5-10 Emty Pallet Stock / Guide Pallet Unit Qty 1 job
5-11 Water Pipe and Shower with Hose (8 Set) Qty 1 job
5-12 Manpower and Packing / Transportation Qty 1 job
6 Mechanical labore cost
6-1 Drawing design Qty 1 job
6-2 In-Site : Assembly Qty 1 job
6-3 In-Site : Test and Adjustment Qty 1 job
6-4 In-Site : Dismantle and Packing Qty 1 job
6-5 In-Site : Transportation Qty 1 job
6-6 Out-Site : Carry In ,Floor marking and Installation Qty 1 job
6-7 Out-Site : Test and Adjustment Qty 1 job
6-8 Out-Site : Stand by Production Qty 1 job
6-9 Out-Site : Transportation Qty 1 job
6-10 Out-Site : Accommodation + Daily Allowance Qty 1 job
7 Software Development labore cost ( In-site )
7-1 Specification design Qty 1 job
7-2 Program PLC design and Development [ Filling zone ] Qty 1 job
7-3 Program PLC design and Development [ Pallatizer zone ] Qty 1 job
7-4 Software Robot Development 1 job
8 Software Development labore cost ( Out-site )
8-1 Program installation Qty 1 job
8-2 Program I/O Check [ Filling zone ] Qty 1 job
8-3 Program I/O Check [ Pallatizer zone ] Qty 1 job
8-4 Program test run & commistioning Qty 1 job
8-5 Program support Qty 1 job
9 Hardware & Equipment
9-1 MR-F5-1600-HI Qty 2 set
Product Dimensions: 2316*1200*2219 mm (MR-F5-1600-HI :Standard befor Customize :2260*1200*2225mm)
Fork Height/Width/Length: 40/132/1237 mm
Rated Load: 1600 kg
Max. Lifting Height: 4500 mm (Standard befor Customize :3952mm)
Running Speed(rated load/empty): 1.2/1.5 m/s
Navigation Mode: L-SLAM
Battery: 48V125Ah LiFePO4
Laser: front HIROBOT self-developed obstacle avoidance laser + domestic 2D navigation laser
Safety Protection: bumper strip + front, left & right obstacle avoidance laser + emergency stop button + so
9-2 MR-RA-CH-48/60(CE) Qty 2 set
AC Input Voltage: 100-127/200-240 VAC
AC Input Frequency: 50/60 Hz
Max. Input Current: 25 A
DC Output Voltage: 48 V
Max. Output Current: 30/60 A"
9-3 Implementation toolbox Air tickets for engineer FMR- Implementation tool box Qty 1 set
9-4 Zebra ZD421 Printing method: Thermal transfer and direct thermal Qty 1 set
9-5 DS-MDT201 Android10, 5.5" Screen,5MP+13MP,4GB+64GB,Wi-Fi,4G,NFC,GPS,4900mAh,IP68,OCR **Warranty 2years 2 set
10 Software
10-1 RCS PostgreSQL included, and WCS Qty 1 set
11 Human Resource Fee
11-1 Site Service for AMR implementation and commissioning Qty 1 job
12-14 persons, 5 days/week, 9am to 6pm
1. Rack assembly
2. QR code implementation
3. Rack code implementation
4. Bin code implementation
5. Inclusive of 3 scissors lift rental
12 Transportation
12-1 20Ft container Ocean Freight + Local customs Fee + Local transportation fee Qty 1 set
12-2 Freight Insurance Qty 1 set
12-3 Import Duty (AMR) Qty 1 set
12-4 Import Duty (Charger and accessories) Qty 1 set
13 Import Duty (Charger and accessories)
13-1 Supplier Manpower and Packing / Transportation Qty 1 set
13-2 AGF Programing installation Qty 1 set
13-3 Server / UPS and server license **Warranty 3years Qty 1 set
14 Installation
14-1 In-Site : Dismantle and Packing Qty 1 set
14-2 In-Site : Transportation Qty 1 set
14-3 Out-Site : Carry In ,Floor marking and Installation Qty 1 set
14-4 Out-Site : Test and Adjustment Qty 1 set
14-5 Out-Site : Stand by Production Qty 1 set
14-6 Out-Site : Transportation Qty 1 set
14-7 Out-Site : Accommodation + Daily Allowance Qty 1 set
14-8 Carts for Notebook ( Operate AGF ) Qty 1 set
15 Primary Supply Cost
15-1 Power Cable for Primary Supply Qty 1 set
Remark :
1) 25% DP upon PO
2) 25% After completion of requirements definition phase & When arranging parts 3) 20% After Hardware Arrangement Completed / Before Factory Installation Work 4) 20% After installation
5) 10% After handover *Warranty start *1-year warranty This specification is in accordance with the sign drawings. Anything other than the drawings is not included in the Quotation. Power System Condition / Base design: 380 V 3-phase
Updated by Waraporn Promsopa 4 days ago
- Subject changed from [PJ2600104] Robot Palletizer JCU (THAILAND) CO., LTD to [PJ260104] Robot Palletizer JCU (THAILAND) CO., LTD