[PJ240025] Install Andon system for monitoring RP-EPS1 #1 PLC plan

Added by Ryo Nozaki over 1 year ago. Updated 27 days ago.

Status:
Closed
Priority:
Normal
Start date:
07 Aug 2024
Due date:
15 Feb 2026
Spent time:
(Total: 524.50 h)

Subtasks 23 (0 open23 closed)

Project progress work #699: Electrical DiagramClosedPhatthadon Inthachot07 Aug 202430 Aug 2024

Actions
Project progress work #700: PR Electrical part ClosedPhatthadon Inthachot07 Aug 202430 Aug 2024

Actions
Project progress work #720: Specification and system designClosedNattapol Poeam16 Sep 202430 Nov 2024

Actions
Project progress work #737: [ Installation & Support ] Installation and wiring andon projectClosedNattapong Sukcharoen24 Oct 202411 Nov 2024

Actions
Project progress work #796: [ Wring & Assembly ] Andon monitoring system Control cabinet 3 SetClosedNattapong Sukcharoen24 Oct 202411 Nov 2024

Actions
Project progress work #1096: [Requirement definition]ClosedNattapol Poeam07 Aug 202430 Nov 2024

Actions
Project progress work #1097: [Internal Design]ClosedNattapol Poeam11 Aug 202430 Nov 2024

Actions
Project progress work #1098: [Coding] Backend coding * hold, Waiting for shindengenClosedPhattarapong Kammee16 Jan 202617 Jan 2026

Actions
Project progress work #1397: [Coding] Air flowClosedPhattarapong Kammee

Actions
Project progress work #1398: [Coding] ChillerClosedPhattarapong Kammee

Actions
Project progress work #1399: [Coding] Power meter Closed

Actions
Project progress work #1400: [Coding] Factory monitoringClosedPhattarapong Kammee

Actions
Project progress work #1401: [Coding] Manage meterClosedPhattarapong Kammee

Actions
Project progress work #1402: [Coding] Production monitoringClosedPhattarapong Kammee

Actions
Project progress work #1403: [Coding] AnalysisClosedPhattarapong Kammee

Actions
Project progress work #1404: [Coding] Manage peak rateClosedPhattarapong Kammee

Actions
Project progress work #1405: [Coding] Manage targetClosedPhattarapong Kammee

Actions
Project progress work #1406: [Coding] Sync data ClosedPhattarapong Kammee

Actions
Project progress work #1407: [Coding] Electric summary ClosedPhattarapong Kammee

Actions
Project progress work #7071: [Coding] Update comment program PLCClosedPanupong Raksakit16 Jan 202617 Jan 2026

Actions
Project progress work #1099: [Installation&On-site support]ClosedNattapol Poeam15 Feb 202615 Feb 2026

Actions
Project progress work #6688: [Installation&On-site support] Arrange Lan cablesClosedPhatthadon Inthachot15 Feb 202615 Feb 2026

Actions
Project progress work #6689: [Installation&On-site support] Install name plateClosedPhatthadon Inthachot15 Feb 202615 Feb 2026

Actions
Actions #1

Updated by Siriporn Nimitmuenwai 9 months ago

  • Subject changed from [PJ240025] Install Andon system for monitoring RP-EPS1 to [PJ240025] Install Andon system for monitoring RP-EPS1 #1 PLC plan
  • Assignee changed from Ryo Nozaki to Nattapol Poeam
Actions #2

Updated by Waraporn Promsopa 2 months ago

  • Project changed from JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. to JTEKT ASIA PACIFIC CO.,LTD.
Actions #3

Updated by Waraporn Promsopa 27 days ago

  • Status changed from New to Closed
Actions