[PJ260005] Camera system Preventive mantianace for P04

Added by Siriwilai Chaiwattanaphon 18 days ago. Updated 17 days ago.

Status:
In Progress
Priority:
Normal
Start date:
13 Jan 2026
Due date:
23 Jan 2026 (11 days late)

Description

Installation fee at onsite (BCR system for ThaiYokorei - Equipment) Q'ty 1Job


Files


Subtasks 6 (3 open3 closed)

Project progress work #4452: [Requirement Definition]ClosedPhatthadon Inthachot13 Jan 202614 Jan 2026

Actions
Project progress work #4453: [Internal drawing]ClosedPhatthadon Inthachot14 Jan 202614 Jan 2026

Actions
Project progress work #4454: [Coding]ClosedPhatthadon Inthachot14 Jan 202614 Jan 2026

Actions
Project progress work #4455: [Installation&On-site support]In Progress15 Jan 202623 Jan 2026

Actions
Project progress work #4456: [Installaton&On-site support] Preventive mantinanceNewPhatthadon Inthachot15 Jan 202615 Jan 2026

Actions
Project progress work #4457: [Installation&On-site support] Report preventive maintenance summaryNewPhatthadon Inthachot19 Jan 202623 Jan 2026