[PJ250078] Operation monitoring system for ShinDengen 100% (DAIICHI JITSUGYO (THAILAND) CO., LTD)

Added by Siriwilai Chaiwattanaphon 5 months ago. Updated 3 days ago.

Status:
Closed
Priority:
Normal
Start date:
17 Nov 2025
Due date:
13 Mar 2026

Subtasks 38 (0 open38 closed)

Project progress work #2784: [Requirement definition]ClosedKonlawat Saechee17 Nov 202530 Nov 2025

Actions
Project progress work #2785: [Internal Design]Closed17 Nov 202504 Feb 2026

Actions
Project progress work #3028: [Internal Design] Software System DesignClosed01 Dec 202514 Dec 2025

Actions
Project progress work #3029: [Internal Design] Hardware system designClosedKonlawat Saechee17 Nov 202523 Nov 2025

Actions
Project progress work #6669: [Internal design] Meeting about 5 screen with DJKClosedPhattarapong Kammee04 Feb 202604 Feb 2026

Actions
Project progress work #2786: [Coding]Closed27 Nov 202513 Mar 2026

Actions
Project progress work #3016: [Coding] Add ScaleClosedThiraporn Amornsirinukorh27 Nov 202505 Jan 2026

Actions
Project progress work #3017: [Coding] Addition estimate time follow planClosedThiraporn Amornsirinukorh27 Nov 202505 Jan 2026

Actions
Project progress work #3018: [Coding] Addition detail "Plan delay, Planned shutdown overtime, OEE" Product by productClosedThiraporn Amornsirinukorh27 Nov 202505 Jan 2026

Actions
Project progress work #3019: [Coding] Add Color OEE (Red, Green)ClosedThiraporn Amornsirinukorh27 Nov 202505 Jan 2026

Actions
Project progress work #3020: [Coding] Add target settingClosedThiraporn Amornsirinukorh27 Nov 202505 Jan 2026

Actions
Project progress work #3021: [Coding] Change color Gray for Breakdown Actual ClosedThiraporn Amornsirinukorh27 Nov 202505 Jan 2026

Actions
Project progress work #3022: [Coding] Manual to Edit Actual (Quantity and Color)ClosedThiraporn Amornsirinukorh27 Nov 202505 Jan 2026

Actions
Project progress work #3023: [Coding] Notification OEE by E-Mail or SmartwatchClosedThiraporn Amornsirinukorh27 Nov 202505 Jan 2026

Actions
Project progress work #3024: [Coding] Change "OEE, Plan delay time; Plan shutdown" lot by lot day per timeClosedThiraporn Amornsirinukorh27 Nov 202505 Jan 2026

Actions
Project progress work #3025: [Coding] Add Import/Export to File CSVClosedPhattarapong Kammee27 Nov 202505 Jan 2026

Actions
Project progress work #3026: [Coding] Addition plan NO OT, Plan Machine Stop, OtherClosedPhattarapong Kammee27 Nov 202505 Jan 2026

Actions
Project progress work #3027: [Coding] Addition time to used and auto endClosedPhattarapong Kammee27 Nov 202505 Jan 2026

Actions
Project progress work #6442: [Coding] Create new webClosedWorawit Khantamool04 Feb 202604 Feb 2026

Actions
Project progress work #6517: [Coding] Meeting about 5 screen with DJKClosedWorawit Khantamool04 Feb 202604 Feb 2026

Actions
Project progress work #6763: [Coding] Create dashboard summary and fixed lineClosedWorawit Khantamool23 Feb 202624 Feb 2026

Actions
Project progress work #6766: [Coding] Onsite update dashboard fixed lineClosedWorawit Khantamool28 Feb 202628 Feb 2026

Actions
Project progress work #6934: [Coding] Fixed the system has encountered a bugClosedWorawit Khantamool11 Mar 202611 Mar 2026

Actions
Project progress work #6987: [Coding] Fixed the problem of line split screen, remark list not showingClosedWorawit Khantamool13 Mar 202613 Mar 2026

Actions
Project progress work #2787: [Installation&On-site support]Closed23 Nov 202530 Jan 2026

Actions
Project progress work #3030: [Installation&On-site support] Hardware installation and wiring Line 2ClosedKonlawat Saechee23 Nov 202524 Nov 2025

Actions
Project progress work #3031: [Installation&On-site support] Software Machine data collection & Configuration Line 2ClosedThiraporn Amornsirinukorh23 Nov 202524 Nov 2025

Actions
Project progress work #3032: [Installation&On-site support] Hardware installation and wiring Line 3,4,5ClosedKonlawat Saechee13 Dec 202514 Dec 2025

Actions
Project progress work #3033: [Installation&On-site support] Software Machine data collection & Configuration Line 3,4,5ClosedThiraporn Amornsirinukorh13 Dec 202514 Dec 2025

Actions
Project progress work #3034: [Installation&On-site support] Software InstallationClosedThiraporn Amornsirinukorh12 Jan 202618 Jan 2026

Actions
Project progress work #3035: [Installatin&On-site support] Teaching for UTClosedKonlawat Saechee19 Jan 202628 Jan 2026

Actions
Project progress work #3036: [Installation&On-site support] User Testing & TrialClosedKonlawat Saechee19 Jan 202628 Jan 2026

Actions
Project progress work #3037: [Installation&On-site support] Supports user feedbackClosedKonlawat Saechee19 Jan 202628 Jan 2026

Actions
Project progress work #3038: [Installation&On-site support] Teaching for Go liveClosedKonlawat Saechee19 Jan 202628 Jan 2026

Actions
Project progress work #3039: [Installation&On-site support] Go live ClosedKonlawat Saechee29 Jan 202630 Jan 2026

Actions
Project progress work #6764: [Issue]Closed27 Feb 202602 Mar 2026

Actions
Project progress work #6765: [Issue] Fix issues dashboard fixed lineClosedWorawit Khantamool27 Feb 202627 Feb 2026

Actions
Project progress work #6781: [Issue] Resolve the issue as reported by the customerClosedWorawit Khantamool02 Mar 202602 Mar 2026

Actions
Actions #1

Updated by Siriwilai Chaiwattanaphon 4 months ago

  • Assignee changed from Ryo Nozaki to Nattapol Poeam
Actions #2

Updated by Siriwilai Chaiwattanaphon 4 months ago

Hardware
1. WDT-5LR-Z2 Network Device 8 unit
2. Linear shaft hardware sets 4 set
3. Assembly cost for internal and accessory 4 job
4. Sensor OMRON 1 set and accessory 4 set

Installation
1. Installation cost for hardware 4 job
2. Parameter setting & installation test 4 job

Actions #3

Updated by Waraporn Promsopa 4 days ago

  • Status changed from In Progress to Closed
Actions #4

Updated by Waraporn Promsopa 3 days ago

  • Status changed from Closed to In Progress
Actions #5

Updated by Waraporn Promsopa 3 days ago

  • Status changed from In Progress to Closed
Actions