18 Oct 2025

16:24 NKT NIPPON KONPO (THAILAND) CO., LTD 6.00 hours (Project progress work #843 (In Progress): [Cording] Warehouse system for business improvement for NKT Android)
Fixed and check issues. Taweesak Prumvised
16:24 THAI INABA FOODS COMPANY LIMITED 2.00 hours (Project progress work #1014 (Closed): [Coding] Warehouse management system handyterminal Java)
Edit tag label. Taweesak Prumvised

17 Oct 2025

17:12 THAI INABA FOODS COMPANY LIMITED 8.00 hours (Project progress work #1014 (Closed): [Coding] Warehouse management system handyterminal Java)
On site UAT test. Taweesak Prumvised
17:11 THAI INABA FOODS COMPANY LIMITED 8.00 hours (Project progress work #1014 (Closed): [Coding] Warehouse management system handyterminal Java)
Fixed punch list after on site UAT Test. Taweesak Prumvised

15 Oct 2025

17:58 THAI INABA FOODS COMPANY LIMITED 8.00 hours (Project progress work #1014 (Closed): [Coding] Warehouse management system handyterminal Java)
Internal test. Taweesak Prumvised

14 Oct 2025

17:06 NKT NIPPON KONPO (THAILAND) CO., LTD 4.00 hours (Project progress work #843 (In Progress): [Cording] Warehouse system for business improvement for NKT Android)
Fixed bugs of loading schedule. Taweesak Prumvised
17:06 THAI INABA FOODS COMPANY LIMITED 4.00 hours (Project progress work #1014 (Closed): [Coding] Warehouse management system handyterminal Java)
Edit condition of AS/RS. Taweesak Prumvised

10 Oct 2025

12:55 THAI INABA FOODS COMPANY LIMITED 4.00 hours (Project progress work #1014 (Closed): [Coding] Warehouse management system handyterminal Java)
HT pegasus test. Taweesak Prumvised
07:07 THAI INABA FOODS COMPANY LIMITED 8.00 hours (Project progress work #1014 (Closed): [Coding] Warehouse management system handyterminal Java)
On site review all functions. Taweesak Prumvised
 